2011年10月16日下午5点,距离下班还有半个小时,珠海LNG项目部的工地上正在进行的塔吊基础混凝土浇筑已经接近尾声。浇筑完成后,测量工复测发现塔吊锚脚的平整度为千分之二,而塔机安装要求为千分之一。塔吊基础锚脚平整度的控制是塔吊竖立后能否垂直的关键,质量技术经理不敢掉以轻心,一边安排人员校正,一边向项目经理汇报。已经5点41分了,接送员工下班的班车已经缓缓开走,但是塔吊基础施工的地点却围满了人,项目经理、
At 16:00 on October 16, 2011, there is still half an hour left from get off work. The ongoing construction of tower crane foundation concrete at the construction site of Zhuhai LNG Project Department is nearing completion. After the pouring is completed, the surveyors found that the flatness of the anchor of the tower crane was 0.2%, while the tower crane installation requirement was one thousandth. Tower crane foundation anchoring leg flatness control is the key to whether the tower crane can be vertical after erection, the quality and technical manager can not take it lightly while arranging personnel calibration while reporting to the project manager. It has been 5:41, and the shuttle bus to and from get off work has been slowly away, but the construction site of the tower crane is full of people, the project manager,