在经历10个月的停产后,我国最大国产化LNG工厂——湖北黄冈500×104m~3/d LNG工厂于2016年10月2日生产出合格LNG产品,复产一次成功,标志着我国LNG工厂在工艺技术设备、运行调控和建设质量等方面完全具备自主开发能力,具备应对不同工况条件下开工运行的能力。此前,昆仑能源有限公司对湖北黄冈500×104m~3LNG工厂复产进行了周密筹划、组织和准备。9月23日9时28分工厂开始
After 10 months’ shutdown, the LNG plant in Huanggang, Hubei Province, which is the largest LNG plant in China, produced qualified LNG products on October 2, 2016. The successful resumption of production indicated that China’s LNG Factories in the process technology and equipment, operation control and construction quality fully equipped with independent development capabilities, with the ability to start operating under different conditions. Earlier, Kunlun Energy Co., Ltd. conducted a thorough planning, organization and preparation for the 500 × 104m ~ 3LNG factory in Hubei Huanggang. At 09:28 on September 23 the factory started