论文部分内容阅读
摘要:武英高速公路罗田至英山段08合同段全线长13.2公里的工程内,土石方填方开挖约217万m3,该工程范围内路基地层为大别山群上部风化至坚硬的片麻岩,风化程度不同的片麻岩开挖施工是工程的重点,论文详细介绍了该工程路基的爆破开挖、路基的填筑、标准和路基的检验标准等,为同类工程的施工提供技术借鉴。
关键词:路基工程风化片麻岩施工技术
Abstract: WuYing highway to YingShan born for 08 contract section 13.2 kilometers long range of engineering in a filled about 2.17 million m3 conditions excavation, the project scope for the upper strata of subgrade dabie mountain weathering to hard gneiss, weathering degree different gneiss excavation is the focus of the project, this paper introduced the roadbed blasting the project of the excavation, the subgrade filling, standard and the roadbed inspection standards, for similar engineering construction to provide the technology reference.
Key words: the subgrade engineering weathering gneiss construction technology
中图分类号:U416.1文献标识码:A 文章编号:
1. 引 言
武汉至英山高速公路是湖北省规划建设的重大交通项目,项目起于武汉市江岸区谌家矶(平安铺),与武汉市规划建设的中环线相接,经武汉市黄陂(三里桥)、新洲区(周铺)和黄冈市团风、浠水、罗田、英山等地,止于鄂皖交界处的英山县大枫树岭(318国道鄂皖交界处的蔡嘉岭以南2公里处),与安徽省规划的岳西至英山高速公路相接。项目建设对于尽早贯通武汉经英山、岳西至合肥高速公路,优化鄂、皖两省公路网布局,加强湖北与安徽等的联系和交流,增强武汉市经济辐射功能,促进武汉城市经济圈的建设,推进沿线地区经济及旅游业的发展,加快全面建设小康社会等方面均具有十分重要的意义。武英高速公路罗田至英山段起于罗田县城关镇以南的范家冲,与武英高速公路新洲至罗田段相接,路线经罗田县骆驼坳镇、凤山镇、匡河乡、英山县的红山镇、杨柳镇,止于大枫树岭,路线全长52.248km。武英高速罗田至英山段08合同起讫桩号K80+000~K93+200,全线长13.2公里,合同段内共设大中桥梁7座,小桥5座,累计长1912.6米;分离式立交桥2座;互通一处;盖板通道26道,盖板涵洞25道,圆管涵18道,钢筋砼拱涵4道;土石方填方约217万m3。 由于工程区域为构造侵蚀剥蚀丘陵区,沿线自然标高大约在65至188m之间,相对高差最大为123m,其区内岩层多为大别山群上部地层,为坚硬岩石工程地质岩组。因此工程区域内路基的施工是工程的重难点之一,论文详细介绍了该工程路基的施工技术,以期为同类工程的施工提供技术借鉴。
2. 工程地质概况及工程重难点分析
2.1 工程概况
武英高速公路第08合同段路线走向大致为东西向,起点位于罗田县至浠水公路罗河湾附近,由此向东,在K80+411处桥梁横跨上界河与新318国道;在K91+576处,设汪家湾高架桥跨越开阔的徐家河河谷后,接上大河岸互通,到达本标段终点K93+200(罗田县凤山镇对面湾村)。工程区域交通比较方便,区内干线公路有罗田至浠水公路、新318国道、107省道、309县道,通过村镇之间、村村之间的机耕道与公路连接,形成了比较畅通的山区农村交通网。工程区域属亚热带大陆性湿润性气候, 冷暖交替,四季分明,光照充足,热量丰富,降雨充沛;年平均气温16.3℃,极端最高气温40.8℃,极端最低气温-14.3℃,无霜期较长,年无霜期237~238天;年平均降雨量1223 mm~1493 mm ,6、7月份多为偏南风,其余月份多为北风或东北风,年平均风速2.1~3.2m/s,最大风速29.63m/s,最大风力可达10级。
工程区域为构造侵蚀剥蚀丘陵区,沿线地貌为丘陵、冲沟、河流地貌,地形为鸡爪地形,由平台状低矮残丘和冲沟相间组成。公路沿线自然标高大约在65至188m之间,相对高差最大为123m;最高点在K90+820右20m处,最低点在上界河。工程区域属于北东向大别山复式穹状背斜南翼的浠水褶皱束,构造线为北东-南西向的弧形线。区内岩层多为大别山群上部地层,属早元古代的片麻岩,系坚硬岩石工程地质岩组;岩体风化带发育齐全,地表广泛出露,第四系松散堆积物厚度0~10m。
2.2 工程重难点分析
本工程设计标准为山岭重丘区双向四车道高速公路,设计速度100公里/小时,路基宽度双向四车道26m,汽车荷载按汽-1级考虑。本路段地形复杂,相对高差大,属典型的重山丘地形。既有乡村机耕道路窄,陡弯多,仅能通过一台小型车辆,大型施工车辆及拖车不能正常行驶,加之机耕道路一侧为天然排水河沟,另一侧为稻田,不具备扩建条件,所以现有机耕既有道路不能满足大型机械设备进出场的要求,正式开工之前施工便道需拉通,既有的道路需进行维护方可使用,由于线路较长,过往的重车较多,便道在使用过程中要定期维护,以防侵入周边农田及影响正常施工。所以便道的修建和维修是重点。本标段的路基挖土方约80万m3,挖石方约126万m3,填方约217万 m3,需爆破的石方工程量大;路基压实度标准较高,比施工规范要求提高1个百分点,因此路基的施工技术是施工的重点之一。
3. 风化片麻岩路基施工技术
3.1 路基整体施工方案
武英高速罗田至英山段08段为构造侵蚀剥蚀丘陵区,沿线自然标高大约在65至188m之间,相对高差最大为123m,区内岩层多为大别山群上部地层,为坚硬岩石工程地质岩组,土石方填方约217万m3。为确保施工工期,合理调配全线土石方,尤其是运距较长地段,要提前对挖余方和临近需要的借填方进行量化预计,再合理分配调配路线,结合施工机械和人员的合理配套,保证土石方施工持续有序的进行,尽量避免出现误车现象。同时,路基土石方施工中与石方爆破的紧密配合,合理划分爆破作业区和土、石方施工作业区,相互衔接,合理调度,使机械资源得到最充分的利用,保证土石方施工工期的正常进行。
为达到设计要求的路基压实度,采用以下几项措施:一是根据填层区段,合理选择填料;二是严格控制壓实时的填土含水量,在接近最佳含水量±2%时碾压;三是适当减少虚铺厚度、增加碾压遍数;四是利用大型羊足碾进行终压。
3.2路基施工
本合同段路基土方工程具有数量大、工期紧、线路长等特点。主要工程数量如下:路基挖土方80.6万m3,挖石方126.9万m3,利用土方70万m3,利用石方138万m3,借土填方14万m3。
3.2.1 取弃土场规划
首先复核设计指定的取弃土场。距离本合同段取土场共有2处:一处为K84+300右侧100m;一处为GK0+550右侧100m。弃土场设在K90+650左侧200m。取弃土场使用前对运输便道进行现场踏勘,对不能满足施工需要的运输便道进行加宽,加固,使之不影响取弃土的正常进行。根据全线的取弃土量对取弃土场进行规划,确定经济、合理的取弃土范围和高度,采用开挖排水沟、四周浆砌挡土墙、植草、植树等方法对取弃土场进行防护。取土场使用时先将表层耕植土推至规划点集中堆放,同时将路基施工中清除的腐殖土也运至规划点集中堆放,以备取弃土场用完后绿化工程和复耕使用。
3.2.2 路基挖方
大规模进行挖方施工前,先进行长度不小于100米的挖方试验段施工,通过试验段确定开挖后形成的边坡坡率和断面形式,并报监理工程师批准。
测量放样,首先复测导线点,恢复线路中心桩,确定开挖边线并设立施工标志,开挖前完善路堑两侧排水系统。土方开挖,土方开挖采用挖掘机挖土,自卸汽车运土。开挖中如发现土层性质有变化时,修改挖方边坡并及时报监理工程师审批。土方开挖自上而下进行,杜绝超挖或欠挖。石方开挖,石方介定采用不小于110.3KW(150马力)推土机、单齿松土器无法松动,须用爆破或用钢纤大锤或用气钻方法开挖的,以及体积大于或等于1m3 的孤石为石方。
3.2.3 爆破总体方案
石方开挖采用光面爆破技术,对于较缓的山体,先用推土机盘山打道至山顶,从上至下揭出盖山土形成较大的工作面,紧接着潜孔钻机上至平台进行钻孔作业。对于较陡的山体,大型机械无法上去,采用小型钻机打眼爆破,人工清理2~3个梯段高度后,修筑临时便道。
当路堑较深时,横向分成几个台阶进行开挖;路堑即长又深时,纵向分段分层开挖,每层先挖出一通道,然后开挖两侧使各层有独立的出土道路和临时排水设施。
⑴ 炮眼布置:尽量缩小眼口和开挖轮廓线的距离,严格控制钻孔精度。当地面起伏不平时先进行场地平整后根据平整后的地面调整炮孔深度,控制误差在允许范围内。采用较小眼距,按炮眼直径的16倍左右考虑,炮眼位置偏差不超过两倍炮孔直径。方向误差不超过3%。根据不同的石质情况决定最小抵抗线。
⑵ 装药:炸药采用低威力并加工成小直径药卷的炸药。除在眼底用一节标准直径的起爆药卷外,其它采用径向直径孔隙装药或药卷之间有空隙的纵向间隔装药,并控制每米长度上的装药量,以起缓冲爆破作用。装药前将孔内残渣吹净,有水的炮孔要将水吹出。采用同段毫秒雷管微差顺序起爆。
⑶ 盲炮处理:如果产生盲炮,立即封锁现场,组织施工人员针对装药时的具体情况找出拒爆原因,采取相应措施处理。处理盲炮采用二次爆破法、炸毁法及冲洗法等三种办法。属于漏点火的拒爆药包,可再找原来的导火索、导爆管或雷管脚线,经检查确认完好后,进行二次起爆。
3.2.4 路基填方
填土路基填筑施工工艺框图见图1所示。先进行不小于100m的填土路基试验段施工,试验段初步确定为K89+780~K89+880段,通过试验段确定施工机械的配置、适宜的松铺厚度、相应的碾压遍数和合理的施工组织,报监理工程师批准后,开始大规模施工。采取横断面全宽纵向分层的填筑方法。填料运输采用挖掘机(或推土机配装载机)挖装土方,由自卸汽车运送到施工现场,在陡坡路堤,要先用推土机推出汽车便道以便运输填料,然后由低洼处逐层往上填筑,确保路堤填筑质量。当原地面高低不平且坡度小于1:10时,先从最低处分层填筑,坡度大于等于1:10处挖设台阶后自低向高分层填筑,台阶宽度不小于2m,
圖1. 路基填筑施工工艺框图
台阶顶做成2~5%的内倾斜坡。对于填土路堤,分层平行摊铺,分层压实,每层松铺厚度按试验路段压实试验的填土厚度的90%控制,且最小层厚度大于10cm以保证结构层的整体性。为保证路堤边缘的压实度、边坡的稳定性,采用先超宽填筑碾压,待路堤成型后进行刷坡,路基每边超填宽度30cm左右。填筑时局部无法采用大型碾压设备的地方采用辅助设备进行补充碾压。用不同填料填筑路基时,每一水平层的全宽采用同一种材料填筑,避免各种填料混杂填筑。每种填料层总厚度不得小于50cm。填至路床顶面最后一层的压实厚度不能小于10cm。
摊铺整平:填筑区段每完成一层填土后,及时采用大型推土机初平,并将填筑表面做成2%~4%横坡,再用平地机精平,采用拉线和打方格网的办法保证摊铺厚度一致,做到摊铺面在纵向和横向平顺均匀,以保证压路机轮表面能均匀接触地面进行碾压,达到碾压效果。在摊铺平整的同时,用推土机对路肩进行初步压实,以保证压路机进行碾压时,路肩不致发生滑坡。
碾压:为尽量减小路基沉降,保证路基、路面强度结构稳定,必须严格控制填土的压实度,保证路基压实达到设计规定的压实度。路基碾压必须按标准击实试验所得的最佳含水量±2%时进行碾压,同时用最大干密度进行质量控制。压实前由技术人员进行检查,确认分层厚度,平整程度符合要求后进行碾压。填土压实作业采用振动压路机。压路机按照压实部位密实度标准、填层厚度及控制压实遍数,沿线路纵向进行碾压,横向行与行之间重叠40~50cm,前后相邻两段间重叠1.5~2.0m。压实遍数由试验人员根据试验段确定的压实参数确定。压实后若密实度试验不合格时要重新压实后再做试验,直到合格为止。
3.3 路基检测
当路基分层填筑压实完成后,及时进行路基压实度检测并报监理工程师。施工中根据规范要求进行压实度试验。压实度的检测采用核子密度仪、灌砂法、环刀法等多种方法联合检测。检测分二级进行,先项目经理部自检,合格后报监理工程师检验。检查主要项目包括:施工准备、基底处理、机具、填料、含水量、分层厚度和压实度等。经检验合格批准后进行下一层的填筑。施工中做到分层填筑,分层推平,分层压实,分层检测,直到路基填筑至设计标高。对于高填方路堤和软(弱)土层较厚路段进行稳定及沉降观测,按要求设置观测管和观测桩。
3.4 路基整修
路基土石方工程施工基本完毕后,检查测量路基面的中心线和标高,以及路基宽度和边坡度,进行路基整形。边坡整形用机械配合人工自上而下进行,基床面用平地机碾压刮平。整形后的路基表面,除压实和平整机械外,不得行驶其它机械和车辆,整形完毕后的路基范围不得堆废弃杂物。整形后的路堤除符合规范要求的质量标准外,还要符合如下要求:路基表面平整,边线顺直,边坡面稳定不滑坡,曲线圆顺,表面无明显碾压轮迹。
4. 结 论
武英高速公路罗田至英山段08合同段全线长13.2公里,合同段内土石方填方约217万m3,工程区域内沿线相对高差最大为123m,其地层为大别山群上部坚硬岩石及其风化层,区域内的路基施工是工程的重难点之一,论文详细介绍了该工程路基的施工技术,以期为同类工程的施工提供技术借鉴。
参考文献
高速公路路基设计与施工[S].北京:人民交通出版社,1999.
王忠兴.谈公路路基工程施工管理[J].黑龙江交通科技,2006,(4).
张平,范华.浅谈市政道路施工质量控制[J].科技创新导报,2009(1).
谭超华.谈某市政道路的施工方法及质量控制[J].四川建材,2009(1).
刘吉士,阎洪河.公路路基施工技术[M].北京:人民交通出版社,2003.
JTJ 033-95 公路路基施工技术规范[S].
蔡文广.公路路基排水设施施工技术综述[J].科技致富向导,2010,(05):37-38.
郭明富.路基工程质量不足的成因及处治措施[J].交通世界(建养.机械),2010,(08):165-166.
殷明.路基工程质量的成因及处治措施[J].交通世界(建养.机械),2010,(11):89-90.
刘健.浅论城市道路路基施工程序及施工要点[J].山西建筑,2010,(17):34-35.
关键词:路基工程风化片麻岩施工技术
Abstract: WuYing highway to YingShan born for 08 contract section 13.2 kilometers long range of engineering in a filled about 2.17 million m3 conditions excavation, the project scope for the upper strata of subgrade dabie mountain weathering to hard gneiss, weathering degree different gneiss excavation is the focus of the project, this paper introduced the roadbed blasting the project of the excavation, the subgrade filling, standard and the roadbed inspection standards, for similar engineering construction to provide the technology reference.
Key words: the subgrade engineering weathering gneiss construction technology
中图分类号:U416.1文献标识码:A 文章编号:
1. 引 言
武汉至英山高速公路是湖北省规划建设的重大交通项目,项目起于武汉市江岸区谌家矶(平安铺),与武汉市规划建设的中环线相接,经武汉市黄陂(三里桥)、新洲区(周铺)和黄冈市团风、浠水、罗田、英山等地,止于鄂皖交界处的英山县大枫树岭(318国道鄂皖交界处的蔡嘉岭以南2公里处),与安徽省规划的岳西至英山高速公路相接。项目建设对于尽早贯通武汉经英山、岳西至合肥高速公路,优化鄂、皖两省公路网布局,加强湖北与安徽等的联系和交流,增强武汉市经济辐射功能,促进武汉城市经济圈的建设,推进沿线地区经济及旅游业的发展,加快全面建设小康社会等方面均具有十分重要的意义。武英高速公路罗田至英山段起于罗田县城关镇以南的范家冲,与武英高速公路新洲至罗田段相接,路线经罗田县骆驼坳镇、凤山镇、匡河乡、英山县的红山镇、杨柳镇,止于大枫树岭,路线全长52.248km。武英高速罗田至英山段08合同起讫桩号K80+000~K93+200,全线长13.2公里,合同段内共设大中桥梁7座,小桥5座,累计长1912.6米;分离式立交桥2座;互通一处;盖板通道26道,盖板涵洞25道,圆管涵18道,钢筋砼拱涵4道;土石方填方约217万m3。 由于工程区域为构造侵蚀剥蚀丘陵区,沿线自然标高大约在65至188m之间,相对高差最大为123m,其区内岩层多为大别山群上部地层,为坚硬岩石工程地质岩组。因此工程区域内路基的施工是工程的重难点之一,论文详细介绍了该工程路基的施工技术,以期为同类工程的施工提供技术借鉴。
2. 工程地质概况及工程重难点分析
2.1 工程概况
武英高速公路第08合同段路线走向大致为东西向,起点位于罗田县至浠水公路罗河湾附近,由此向东,在K80+411处桥梁横跨上界河与新318国道;在K91+576处,设汪家湾高架桥跨越开阔的徐家河河谷后,接上大河岸互通,到达本标段终点K93+200(罗田县凤山镇对面湾村)。工程区域交通比较方便,区内干线公路有罗田至浠水公路、新318国道、107省道、309县道,通过村镇之间、村村之间的机耕道与公路连接,形成了比较畅通的山区农村交通网。工程区域属亚热带大陆性湿润性气候, 冷暖交替,四季分明,光照充足,热量丰富,降雨充沛;年平均气温16.3℃,极端最高气温40.8℃,极端最低气温-14.3℃,无霜期较长,年无霜期237~238天;年平均降雨量1223 mm~1493 mm ,6、7月份多为偏南风,其余月份多为北风或东北风,年平均风速2.1~3.2m/s,最大风速29.63m/s,最大风力可达10级。
工程区域为构造侵蚀剥蚀丘陵区,沿线地貌为丘陵、冲沟、河流地貌,地形为鸡爪地形,由平台状低矮残丘和冲沟相间组成。公路沿线自然标高大约在65至188m之间,相对高差最大为123m;最高点在K90+820右20m处,最低点在上界河。工程区域属于北东向大别山复式穹状背斜南翼的浠水褶皱束,构造线为北东-南西向的弧形线。区内岩层多为大别山群上部地层,属早元古代的片麻岩,系坚硬岩石工程地质岩组;岩体风化带发育齐全,地表广泛出露,第四系松散堆积物厚度0~10m。
2.2 工程重难点分析
本工程设计标准为山岭重丘区双向四车道高速公路,设计速度100公里/小时,路基宽度双向四车道26m,汽车荷载按汽-1级考虑。本路段地形复杂,相对高差大,属典型的重山丘地形。既有乡村机耕道路窄,陡弯多,仅能通过一台小型车辆,大型施工车辆及拖车不能正常行驶,加之机耕道路一侧为天然排水河沟,另一侧为稻田,不具备扩建条件,所以现有机耕既有道路不能满足大型机械设备进出场的要求,正式开工之前施工便道需拉通,既有的道路需进行维护方可使用,由于线路较长,过往的重车较多,便道在使用过程中要定期维护,以防侵入周边农田及影响正常施工。所以便道的修建和维修是重点。本标段的路基挖土方约80万m3,挖石方约126万m3,填方约217万 m3,需爆破的石方工程量大;路基压实度标准较高,比施工规范要求提高1个百分点,因此路基的施工技术是施工的重点之一。
3. 风化片麻岩路基施工技术
3.1 路基整体施工方案
武英高速罗田至英山段08段为构造侵蚀剥蚀丘陵区,沿线自然标高大约在65至188m之间,相对高差最大为123m,区内岩层多为大别山群上部地层,为坚硬岩石工程地质岩组,土石方填方约217万m3。为确保施工工期,合理调配全线土石方,尤其是运距较长地段,要提前对挖余方和临近需要的借填方进行量化预计,再合理分配调配路线,结合施工机械和人员的合理配套,保证土石方施工持续有序的进行,尽量避免出现误车现象。同时,路基土石方施工中与石方爆破的紧密配合,合理划分爆破作业区和土、石方施工作业区,相互衔接,合理调度,使机械资源得到最充分的利用,保证土石方施工工期的正常进行。
为达到设计要求的路基压实度,采用以下几项措施:一是根据填层区段,合理选择填料;二是严格控制壓实时的填土含水量,在接近最佳含水量±2%时碾压;三是适当减少虚铺厚度、增加碾压遍数;四是利用大型羊足碾进行终压。
3.2路基施工
本合同段路基土方工程具有数量大、工期紧、线路长等特点。主要工程数量如下:路基挖土方80.6万m3,挖石方126.9万m3,利用土方70万m3,利用石方138万m3,借土填方14万m3。
3.2.1 取弃土场规划
首先复核设计指定的取弃土场。距离本合同段取土场共有2处:一处为K84+300右侧100m;一处为GK0+550右侧100m。弃土场设在K90+650左侧200m。取弃土场使用前对运输便道进行现场踏勘,对不能满足施工需要的运输便道进行加宽,加固,使之不影响取弃土的正常进行。根据全线的取弃土量对取弃土场进行规划,确定经济、合理的取弃土范围和高度,采用开挖排水沟、四周浆砌挡土墙、植草、植树等方法对取弃土场进行防护。取土场使用时先将表层耕植土推至规划点集中堆放,同时将路基施工中清除的腐殖土也运至规划点集中堆放,以备取弃土场用完后绿化工程和复耕使用。
3.2.2 路基挖方
大规模进行挖方施工前,先进行长度不小于100米的挖方试验段施工,通过试验段确定开挖后形成的边坡坡率和断面形式,并报监理工程师批准。
测量放样,首先复测导线点,恢复线路中心桩,确定开挖边线并设立施工标志,开挖前完善路堑两侧排水系统。土方开挖,土方开挖采用挖掘机挖土,自卸汽车运土。开挖中如发现土层性质有变化时,修改挖方边坡并及时报监理工程师审批。土方开挖自上而下进行,杜绝超挖或欠挖。石方开挖,石方介定采用不小于110.3KW(150马力)推土机、单齿松土器无法松动,须用爆破或用钢纤大锤或用气钻方法开挖的,以及体积大于或等于1m3 的孤石为石方。
3.2.3 爆破总体方案
石方开挖采用光面爆破技术,对于较缓的山体,先用推土机盘山打道至山顶,从上至下揭出盖山土形成较大的工作面,紧接着潜孔钻机上至平台进行钻孔作业。对于较陡的山体,大型机械无法上去,采用小型钻机打眼爆破,人工清理2~3个梯段高度后,修筑临时便道。
当路堑较深时,横向分成几个台阶进行开挖;路堑即长又深时,纵向分段分层开挖,每层先挖出一通道,然后开挖两侧使各层有独立的出土道路和临时排水设施。
⑴ 炮眼布置:尽量缩小眼口和开挖轮廓线的距离,严格控制钻孔精度。当地面起伏不平时先进行场地平整后根据平整后的地面调整炮孔深度,控制误差在允许范围内。采用较小眼距,按炮眼直径的16倍左右考虑,炮眼位置偏差不超过两倍炮孔直径。方向误差不超过3%。根据不同的石质情况决定最小抵抗线。
⑵ 装药:炸药采用低威力并加工成小直径药卷的炸药。除在眼底用一节标准直径的起爆药卷外,其它采用径向直径孔隙装药或药卷之间有空隙的纵向间隔装药,并控制每米长度上的装药量,以起缓冲爆破作用。装药前将孔内残渣吹净,有水的炮孔要将水吹出。采用同段毫秒雷管微差顺序起爆。
⑶ 盲炮处理:如果产生盲炮,立即封锁现场,组织施工人员针对装药时的具体情况找出拒爆原因,采取相应措施处理。处理盲炮采用二次爆破法、炸毁法及冲洗法等三种办法。属于漏点火的拒爆药包,可再找原来的导火索、导爆管或雷管脚线,经检查确认完好后,进行二次起爆。
3.2.4 路基填方
填土路基填筑施工工艺框图见图1所示。先进行不小于100m的填土路基试验段施工,试验段初步确定为K89+780~K89+880段,通过试验段确定施工机械的配置、适宜的松铺厚度、相应的碾压遍数和合理的施工组织,报监理工程师批准后,开始大规模施工。采取横断面全宽纵向分层的填筑方法。填料运输采用挖掘机(或推土机配装载机)挖装土方,由自卸汽车运送到施工现场,在陡坡路堤,要先用推土机推出汽车便道以便运输填料,然后由低洼处逐层往上填筑,确保路堤填筑质量。当原地面高低不平且坡度小于1:10时,先从最低处分层填筑,坡度大于等于1:10处挖设台阶后自低向高分层填筑,台阶宽度不小于2m,
圖1. 路基填筑施工工艺框图
台阶顶做成2~5%的内倾斜坡。对于填土路堤,分层平行摊铺,分层压实,每层松铺厚度按试验路段压实试验的填土厚度的90%控制,且最小层厚度大于10cm以保证结构层的整体性。为保证路堤边缘的压实度、边坡的稳定性,采用先超宽填筑碾压,待路堤成型后进行刷坡,路基每边超填宽度30cm左右。填筑时局部无法采用大型碾压设备的地方采用辅助设备进行补充碾压。用不同填料填筑路基时,每一水平层的全宽采用同一种材料填筑,避免各种填料混杂填筑。每种填料层总厚度不得小于50cm。填至路床顶面最后一层的压实厚度不能小于10cm。
摊铺整平:填筑区段每完成一层填土后,及时采用大型推土机初平,并将填筑表面做成2%~4%横坡,再用平地机精平,采用拉线和打方格网的办法保证摊铺厚度一致,做到摊铺面在纵向和横向平顺均匀,以保证压路机轮表面能均匀接触地面进行碾压,达到碾压效果。在摊铺平整的同时,用推土机对路肩进行初步压实,以保证压路机进行碾压时,路肩不致发生滑坡。
碾压:为尽量减小路基沉降,保证路基、路面强度结构稳定,必须严格控制填土的压实度,保证路基压实达到设计规定的压实度。路基碾压必须按标准击实试验所得的最佳含水量±2%时进行碾压,同时用最大干密度进行质量控制。压实前由技术人员进行检查,确认分层厚度,平整程度符合要求后进行碾压。填土压实作业采用振动压路机。压路机按照压实部位密实度标准、填层厚度及控制压实遍数,沿线路纵向进行碾压,横向行与行之间重叠40~50cm,前后相邻两段间重叠1.5~2.0m。压实遍数由试验人员根据试验段确定的压实参数确定。压实后若密实度试验不合格时要重新压实后再做试验,直到合格为止。
3.3 路基检测
当路基分层填筑压实完成后,及时进行路基压实度检测并报监理工程师。施工中根据规范要求进行压实度试验。压实度的检测采用核子密度仪、灌砂法、环刀法等多种方法联合检测。检测分二级进行,先项目经理部自检,合格后报监理工程师检验。检查主要项目包括:施工准备、基底处理、机具、填料、含水量、分层厚度和压实度等。经检验合格批准后进行下一层的填筑。施工中做到分层填筑,分层推平,分层压实,分层检测,直到路基填筑至设计标高。对于高填方路堤和软(弱)土层较厚路段进行稳定及沉降观测,按要求设置观测管和观测桩。
3.4 路基整修
路基土石方工程施工基本完毕后,检查测量路基面的中心线和标高,以及路基宽度和边坡度,进行路基整形。边坡整形用机械配合人工自上而下进行,基床面用平地机碾压刮平。整形后的路基表面,除压实和平整机械外,不得行驶其它机械和车辆,整形完毕后的路基范围不得堆废弃杂物。整形后的路堤除符合规范要求的质量标准外,还要符合如下要求:路基表面平整,边线顺直,边坡面稳定不滑坡,曲线圆顺,表面无明显碾压轮迹。
4. 结 论
武英高速公路罗田至英山段08合同段全线长13.2公里,合同段内土石方填方约217万m3,工程区域内沿线相对高差最大为123m,其地层为大别山群上部坚硬岩石及其风化层,区域内的路基施工是工程的重难点之一,论文详细介绍了该工程路基的施工技术,以期为同类工程的施工提供技术借鉴。
参考文献
高速公路路基设计与施工[S].北京:人民交通出版社,1999.
王忠兴.谈公路路基工程施工管理[J].黑龙江交通科技,2006,(4).
张平,范华.浅谈市政道路施工质量控制[J].科技创新导报,2009(1).
谭超华.谈某市政道路的施工方法及质量控制[J].四川建材,2009(1).
刘吉士,阎洪河.公路路基施工技术[M].北京:人民交通出版社,2003.
JTJ 033-95 公路路基施工技术规范[S].
蔡文广.公路路基排水设施施工技术综述[J].科技致富向导,2010,(05):37-38.
郭明富.路基工程质量不足的成因及处治措施[J].交通世界(建养.机械),2010,(08):165-166.
殷明.路基工程质量的成因及处治措施[J].交通世界(建养.机械),2010,(11):89-90.
刘健.浅论城市道路路基施工程序及施工要点[J].山西建筑,2010,(17):34-35.