高碑店变电站工程是一个“标兵”試点工程。为了多快好省地完成这个工程建設任务,我們不仅加强了“质量第一”的思想教育,同时也加强了勤儉建国的思想教育,强調了經济核算工作,因而全面地、均衡地完成了任务。經过驗收,工程质量評为“优”,工程总成本降低了3.31%(上級規定是2.5%),月月按期或超額完成計划,劳动生产率比計划提高了16%。
The Gaobeidian substation project is a pilot project. In order to complete this project construction task more quickly and efficiently, we not only strengthened the “quality first” ideological education, but also strengthened the ideological education of diligent and founding the country, emphasized the work of economic accounting, and thus completed a comprehensive and balanced approach. task. After acceptance, the quality of the project was rated as “excellent”, the total cost of the project was reduced by 3.31% (the upper limit was 2.5%), and the monthly and monthly schedules were completed on schedule or exceeded, and labor productivity increased by 16% over the plan.