“胡椒面”工程不是现在才有,已存在多年,是基本建设中的一大弊端。据对雁北大同县黄土坡地方国营煤矿的调查,其弊端起码有5个:①建设投资严重拖欠。设计要求建设资金1983年给清,结果一直拖到1988年才给完,比原定计划超了5年,超过建设周期1倍多。②材料、设备涨价过猛。由于建设投资不能按施工进度下拨,新井所需要工料及设备的价格,比1980年预算时翻了一番多,只起到原来一半的作用。③施工进度无限延长。
The “pepper noodle” project, which is not now available, has existed for many years and is one of the major drawbacks in capital construction. According to a survey on the state-owned coal mines in Datong County on the Loess Plateau, there are at least five disadvantages: ① There is a serious delinquency in construction investment. Design requirements Construction funds to be cleared in 1983, the result has been dragged to the end of 1988, exceeding the original plan over five years, more than double the construction cycle. ② materials, equipment prices too much. Since investment in construction can not be made according to the construction schedule, the price of materials and equipment needed for Xinjing more than doubled from the budget in 1980, and it only played half its original role. ③ unlimited construction progress.