论文部分内容阅读
1 工程概况孟洲坝水电站位于广东省韶关市北江。电站枢纽由大坝、厂房、船闸、开关站等组成。电站装机44MKW。初步设计总概算(送审本)于1992年9月编制上报。同年10月审查,总概算(审定本)电站枢纽总投资41595万元。其中静态投资33677万元;价差预备费6367万元;建设期还贷利息1551万元;另计列送出工程
1 Project Overview Mengzhou Dam Hydropower Station is located in Shaoguan City, Guangdong Province, North River. Power station hub from the dam, plant, ship lock, switch station and other components. Power station installed 44MKW. The preliminary design of the total budget estimates (submitted to the trial) in September 1992 prepared report. The same year in October review, the total estimated (trial version) power station hub total investment of 415.95 million yuan. Of which static investment 336770000 yuan; Spreads the prepaid fee of 63.67 million yuan; construction loan repayment interest of 15.51 million yuan;