2004年3月2日,南瑞自控公司收到广西平班水电开发有限公司通知书,平班水电站计算机监控系统项目招标结果揭晓,南控自控公司中标,双方将于3月10日正式签订项目合同。平班水电站位于红水河干流南盘江下游,为红水河流域规划梯级开发中的第三级,上游连接天生桥二级水电站,下游连接龙滩水电站。电站装机容量为3×135MW,水库总库容2.78亿 m~3。电站采用计算机监控,按“无人值班”(少人值守)设计。
On March 2, 2004, NARI received a notice from Pingban Hydropower Development Co., Ltd. in Guangxi that the bidding result of the computer monitoring system project of Pingban Hydropower Station was announced and Nantong Automation Co., Ltd. won the bid. The two sides signed the project on March 10 contract. Pingban Hydropower Station is located in the lower reaches of the Nanpan River, the mainstream of the Hongshui River. It is the third level in the cascade development of the Hongshui River Basin. The upper reaches connect to the Tianshengqiao Second Stage Hydropower Station and the downstream reaches Longtan Hydropower Station. Power plant installed capacity of 3 × 135MW, total reservoir capacity of 278 million m ~ 3. Power station using computer monitoring, press “unattended ” (less watch) design.