长春热电二厂系吉林省电力公司下属的热电联产企业,位于吉林省政治、经济、文化、交通中心的长春市,是全市最大的供热热源和供电电源。一期工程安装两台200MW超高压供热机组,供热能力达1505.52×10~6KJ/h,于1991年投入运行,全市集中采暖面积中的53%和电负荷的63%由该厂供给。 1993年电力部批准二期扩建两台300MW供热机组,装机容量将达到
Changchun Thermoelectric No. 2 Plant is a cogeneration company under the Jilin Provincial Electric Power Company. It is located in Changchun City, a political, economic, cultural, and transportation center of Jilin Province. It is the city’s largest source of heat and power. In the first phase of the project, two 200MW ultra-high pressure heating units were installed with heating capacity of 1505.52×10~6KJ/h. They were put into operation in 1991. 53% of the city’s central heating area and 63% of the electric load were supplied by the plant. In 1993, the Ministry of Electric Power approved the second phase of the expansion of two 300 MW heating units, and the installed capacity will reach