在采空区建设电厂时,由于地基情况复杂,对位于采空区各区域的建( 构) 筑物,应采取不同的处理方法,增加防水和抗渗漏措施。当建( 构) 筑物横跨采空区的2 个或2 个以上采空区域时应合理设置变形缝;无法设置变形缝时,基础应做成抗变形整体基础,基底应有足够的柔性。
In the construction of power plants in goafs, due to the complex foundation conditions, different methods should be adopted for the construction of buildings and structures located in various areas of the goafs to increase waterproof and anti-leakage measures. The deformation joints should be set reasonably when the building is across 2 or more goafs in the goaf; when the deformation joints cannot be installed, the foundation should be made anti-deformation as a whole and the foundation should be flexible enough. .