9月10日下午18时45分,随着I93-I104放线区段最后一相导线牵引走板徐徐到位,扎科工程最后一个放线区段完成了导地线展放施工。至此,由国网蒙东经研院建设管理的蒙东扎鲁特~科尔沁500千伏输变电工程(以下简称“扎科工程”)实现了全线贯通,为扎青特高压按期投运提供了重要保。扎科工程途经内蒙古自治区通辽市扎鲁特旗、科尔沁左翼中旗、科尔沁区,线路全长3×94.3公里,按3个单回路并
At 18:45 on September 10, with the last phase of the I93-I104 pay-off section, the traction of the last-phase conductor slowly came into place. The last pay-out section of the ZAKO project completed the construction of the guide ground. At this point, the Mengdong Zhalute-Horqin 500 kV Power Transmission and Transformation Project (hereinafter referred to as “ZAKO Engineering”), constructed and managed by State Grid Mengdong Institute of Research and Development, has been fully implemented and provided for Zhaqing UHV on schedule Important insurance. Zakho engineering via Tongliao City, Inner Mongolia Autonomous Region Zarateut flag, Horqin left wing banner, Horqin district, line length of 3 × 94.3 kilometers, according to three single-loop and