南昌地铁1号线一期工程从2012年7月6日24个站点全线开工建设,历经3年半的时间,于2015年12月26日开通试运营。1号线一期工程始于双港,终于瑶湖,全长28.8 km,设车站24座,途径6个城区,全部采用地下形式敷设,其中规划换乘站5座,总投资210亿元。最长站间距3 080 m,最短站间距585m。南昌地铁1号线采用国标钢轮钢轨制式B型车,每列车6节车厢,共计27列162辆。最高运行速度为80 km/h。列车具备自动驾驶模式和人工驾驶模式,并且具有故障自动诊断功
Nanchang Metro Line 1 project from July 6, 2012 24 sites across the board to start construction, after three and a half years, in December 26, 2015 opening of trial operation. Line 1 Phase I started in Shuanggang, finally Yao Lake, a total length of 28.8 km, located 24 stations, 6 urban areas, all laid underground form, of which planning transfer station 5, a total investment of 21 billion yuan. The longest station spacing 3 080 m, the shortest station spacing 585m. Nanchang Subway Line 1 uses the GB steel Rails B-type cars, each train 6 cars, a total of 27 162. The maximum operating speed is 80 km / h. Train with automatic driving mode and manual driving mode, and with automatic fault diagnosis work