卡拉奇的输变电网现代化计划——“第5个电力计划”正在缓慢起步。原订由亚行援助,1991年年底起动的该项目,由于亚行中途停止援助现在刚落标订货。该项目由地上、地下电缆(132KV、220KV)敷设、断路器和两个气体断路开关设备组成。地下输电电缆的敷设由本国企业Imperial Construction Co.承包。其它设施的提案正在研究中,1994年第一季度订货,1996年完工。 现巴基斯坦正在为第6个电力计划
Karachi’s plan for the modernization of the transmission and distribution network - the “5th Power Plan” is slowly starting. The project, originally scheduled to be aided by ADB, was launched at the end of 1991. As the ADB stopped assistance on the way, it has now just placed an order. The project consists of ground and underground cables (132KV, 220KV) laying, circuit breakers and two gas circuit breakers. The laying of underground transmission cables was contracted by the domestic company Imperial Construction Co. Proposals for other facilities are under study. Orders were made in the first quarter of 1994 and completed in 1996. Pakistan is now working on the sixth power plan