深圳龙华茜坑水厂扩建工程——大型反应沉淀池在满荷载运行约1年后,由于池壁出现明显沉降不均、扭转,局部伸缩缝胶带拉裂、池底渗漏等现象,导致池顶刮泥机轨道变形,使得刮泥机不能正常运行。因此,必须对此进行二次加固处理。在对加固工程长达4年的连续跟踪监测过程中,详细记录了大型反应沉淀池变形的全部数据,据此分析、研究加固处理后的变形规律,并验证池体基础施工设计、结构设计的合理性,为今后类似工程设计、施工提供参考,还可为茜坑水厂反应沉淀池安全、高效地运行提供技术支持。
Longhuaqikeng Waterworks Expansion Project in Shenzhen - Large-scale reaction sedimentation tank operating at full load for about 1 year, due to obvious uneven settlement of the cell wall, torsion, partial expansion joints tape cracking, bottom leakage and other phenomena, resulting in pool Top scraper rail deformation, making the scraper can not operate normally. Therefore, this must be secondary reinforcement. During the continuous follow-up monitoring of the reinforcement project for up to 4 years, all the data of the deformation of the large-scale reaction sedimentation tank are recorded in detail. Based on the analysis, the deformation law after the reinforcement treatment is studied and the basic construction design, structural design of the tank body Rationality for future similar engineering design and construction to provide a reference, but also for Qian pit reactor sedimentation tank safe and efficient operation to provide technical support.