常规的有女儿墙防水屋面,是先砌好女儿墙后进行防水屋面的施工,(或是刚性屋面,或是柔性屋面的防水层的施工)但往往由于施工中的马虎及材料性能的不稳定以及混凝土在女儿墙根部的收缩,很容易在女儿墙根部产生裂缝,引起渗水。近年来我公司在施工有女儿墙的屋面防水层时,进行了探索和改革,效果很好。在屋面多孔板安装后随即做刚性屋面或柔性屋面的防水层,这样施工后能防止女儿墙根部与屋而防水层接触部开裂空壳而引起的内墙渗水,如有发生也仅仅只渗漏到外墙面。
The conventional parapet waterproof roof is constructed by installing the waterproof roof after the parasol is installed (or the rigid roof or the waterproof layer of the flexible roof), but often due to the sloppy construction and unstable material properties. As well as the shrinkage of concrete at the root of the parapet, it is easy to produce cracks in the root of the parapet and cause water seepage. In recent years, our company has explored and reformed the construction of a waterproof layer on a roof with a parapet, and it has achieved good results. After the roofing porous plate is installed, the waterproof layer of the rigid roof or the flexible roof is immediately formed. After the construction, leakage of the inner wall caused by cracking of the shell between the root of the parapet wall and the house and the waterproof layer can be prevented, and only leakage occurs if it occurs. To the outside wall.