1 工程简介淇河盘石头水库泄洪洞工程位于大坝右坝肩,从鸡冠山下横穿而过。进出口开挖边坡处在鸡冠山两侧的陡坡上,边坡开挖高差很大。进口开挖高程为300~211m,在290、278、254、230m高程处设宽3.00m的戗台;出口开挖高程为270~164.5m,在高程245、238、216、214、202、188m设宽3m的戗台,257m高程以上为浆砌石护坡。边坡坡度为1:0.75和1:0.5两种。岩石类型为∈_1~(11)~∈_1~(17)的灰页岩,其中以∈_1~(14)类为主。设计要求进行钢筋网锚喷支护。砂浆锚杆为Φ32的钢筋,长9m,入岩8.9m,外露0.1m,间排距2.5m,梅花形布置。挂网主筋为
1 Project Profile Qihe Pan Shizhu reservoir spillway tunnel project is located at the dam right abutment, crossing the lower corner of the crest. Excavation of import and export slope in Jiguanshan on both sides of the steep slope, slope excavation elevation difference. Entrance excavation elevation 300 ~ 211m, at 290,278,254,230 m elevation set wide 3.00m taiwan; export excavation elevation of 270 ~ 164.5m, at an elevation of 245,238,216,214,202,188 m Set a wide 3m taiwan, 257m above the masonry slope protection. Slope slope of 1: 0.75 and 1: 0.5 two. Gray shale with rock types ∈_1 ~ (11) ~ ∈_1 ~ (17), of which ∈_1 ~ (14) are dominant. Design requirements for steel mesh anchor spray support. Mortar anchor Φ32 for the reinforcement, length 9m, into the rock 8.9m, exposed 0.1m, row spacing 2.5m, plum-shaped layout. Main network for the network