7月22日,国家电网公司召开2015年农电重点工作推进会,贯彻公司年中工作会议精神,总结上半年农电工作,安排下半年农电重点任务,加快农村电网发展,强化县供电企业管理,确保全面完成全年农电各项任务。农网改造升级工程快速推进,2014年国家下达的农网工程基本完成,2015年农网工程投资完成53.4亿元,计划完成率21.7%,物资到货率26.8%,同比分别提高9.4个和2.7个百分点。公司提前半年完成了国家能源局下达的《全面解决无电人口用电问题
On July 22, SGCC held 2015 key work promotion conference for rural power, implemented the spirit of the mid-year work conference, summarized the work of rural power in the first half of the year, arranged the key tasks of rural power in the second half of the year, accelerated the development of rural power grids and strengthened the county power supply enterprises Management, to ensure the full implementation of all tasks of rural power throughout the year. In 2014, the rural grid construction completed by the state was completed. In 2015, the investment in rural grid construction completed 5.34 billion yuan, with a planned completion rate of 21.7% and a material arrival rate of 26.8%, up 9.4 and 2.7 respectively as compared with the same period of last year A percentage point. Six months ahead of schedule the company completed the National Energy Board issued a "comprehensive solution to the problem of electricity consumption without electricity