黑河市处于高寒地区,年平均气温在-1℃以下.最长结冰期173天,最大冰厚1.48m。一些水工建筑物,如水塔、工作桥桥墩等常被静冰压力破坏。黑河市水利局在黑龙江省水科所协助下,用聚苯乙烯硬质泡沫板作保温材料,防止建筑物周围结冰,从而防止了静冰压力对水工建筑物的破坏。经3年实践考验,效果很好。该法比人工破冰方法经济,可靠,施工也简便,为寒区水工建筑物防治静冰害,开辟了新的途径。
Heihe City is in the alpine region, the annual average temperature below -1 ℃. The longest period of freezing 173 days, the maximum ice thickness 1.48m. Some hydraulic structures, such as water towers, bridge piers and other work is often static ice pressure damage. Heihe City Water Conservancy Bureau in Heilongjiang Province, with the assistance of water, with polystyrene rigid foam board for insulation materials to prevent icing around the building, thereby preventing the static ice pressure on the hydraulic construction of the destruction. After three years of practical tests, the effect is very good. The method is more economical and reliable than the manual ice-breaking method, and is also simple in construction. It opens up new avenues for the prevention and control of static ice damage in hydraulic structures in cold areas.