在加拿大萨省动力公司(简称萨动)的白杨河电站(简称白站)1号机组上进行了Tampella LIFAC除硫工艺“全容量示范装置”试验。1990年10月到12月进行了评价工艺脱硫性能的参数试验。1990年12月到1991年7月进行了评价其对电厂运行影响的1500小时“可运行性”试验。对LIFAC工艺的初投资及运行费用,以示范机组为基础进行了估算。基于白杨河的工艺成就,萨动已布置在它建设中的仙德电站中安装LIFAC装置,它在1997年夏季启动。
The “Full Capacity Demonstration Unit” test of the Tampella LIFAC desulfurization process was carried out on Unit 1 of Baiyanghe Power Station (referred to as White Station) of Sask power Co., October 1990 to December to evaluate the process of desulfurization performance parameters of the test. A 1,500-hour “runnability” test to evaluate its impact on plant operation was conducted from December 1990 to July 1991. The initial investment and operating costs of the LIFAC process were estimated based on demonstration units. Based on the technological achievements of Poplar River, Sa move has been installed in its construction Xiande power station installed LIFAC device, which started in the summer of 1997.