放射性排风中心治理工程为新建111-2#排风中心替代现已无法满足需要的111#、111-1#排风中心的所有功能以及近期新增工号的排风要求,关闭111#和111-1#工号及现有烟囱,封闭原室外排风管道。本项目主要由排风中心主体厂房、60m烟囱和至各核设施的室外排风管道组成。本项目于2007年8月正式开工,2007年年底完成烟囱和主厂房主体结构,2008年年底全面开展安装工作,2009年年底主厂房安装工作完成,2010年9月份完成了除管道交叉和接口外的所有
Radioactive exhaust center management project for the new 111-2 # exhaust center to replace the existing 111 #, 111-1 exhaust center can not meet the needs of all the functions and the recent addition of new work No. exhaust requirements, shut down 111 # and 111-1 # # and existing chimney, closed the original outdoor exhaust pipe. The project is mainly composed of the main exhaust workshop, 60m chimney and outdoor exhaust pipe to each nuclear facility. The project was officially started in August 2007, the end of 2007 to complete the main structure of the chimney and the main plant, the full implementation of the installation work by the end of 2008, the main plant installation work completed by the end of 2009, completed in September 2010 in addition to pipe crossings and interfaces all of