2016年11月24日,江西丰城发电厂三期扩建工程发生冷却塔施工平台坍塌特别重大事故,造成73人死亡、2人受伤,直接经济损失10197.2万元。调查认定,江西丰城发电厂“11.24”冷却塔施工平台坍塌特别重大事故是一起生产安全责任事故。一、基本情况(一)江西丰城发电厂三期扩建工程概况。1.工程总体概况。江西丰城发电厂三期扩建工程建设规模为2×1000MW发电机组,总投资额为76.7亿元。其
November 24, 2016, Jiangxi Fengcheng Power Plant Phase III expansion project cooling tower construction platform collapsed a particularly serious accident, killing 73 people were killed and 2 were injured, the direct economic loss of 101.972 million yuan. Survey found that Jiangxi Fengcheng Power Plant “11.24 ” cooling tower construction platform collapse is a particularly serious accident is a production safety responsibility accident. First, the basic situation (A) Jiangxi Fengcheng Power Plant Phase III expansion project overview. 1. Overall project overview. Jiangxi Fengcheng Power Plant Phase III expansion project construction scale of 2 × 1000MW generating units, with a total investment of 7.67 billion yuan. its