湖南省藏冮县春阳滩水电站,设计装机4×8800千瓦工程总造价3200万元。如果按过去国家部分投资补助,其余靠县自筹解决,则县财力物力有限,势必延长建设周期,加重群众负担,针对这种情况,经省地县研究决定,采取省地县三级联办型式。第一期工程包括大坝及厂房土建,37公里110千伏线路和送变电工程,一号机投产。所需资金2585万元。三级联办采取投资分摊,折价入股,签订合同规定省投资820万元,(一半
The Chunyangtan hydropower station in the Zangzi County, Hunan Province, has a total installed cost of 32 million yuan for the 4×8800 kilowatts of the project. If part of the state’s investment subsidies in the past were to be resolved by the county’s self-financing, the county’s financial and material resources will be limited, which will inevitably increase the construction period and increase the burden on the people. In response to this situation, the province’s prefectures and counties have decided to take three provinces and counties. Type. The first phase of the project included dam and factory buildings, 37 km of 110 kV lines and power transmission and transformation projects, and the production of Unit 1 was put into operation. The required funds are 25.85 million yuan. The three cascade offices will adopt investment sharing, discount the shares, and sign the contract to provide provincial investment of 8.2 million yuan (half