摘要:经济的快速发展带动了社会的进步,在高速发展的过程中对于电能的需求也在增加,但是当前输配电线路不能够满足需求,这就需要架设新的线路,以提高输配电线路在运行过程中的可靠性和稳定性。本文就以此为出发点,从线路架设施工的工序和方法进行论述。
关键字:输配电线路;架设施工工序;架设方法
Abstract: The rapid economic development led to the progress of society, in the process of rapid development in the demand for electricity is also increasing, but the current transmission and distribution lines are not able to meet the demand, which required the installation of new lines, in order to improve transmission and distribution the line is in operation reliability and stability. In this paper, as a starting point, from the line erection processes and methods were discussed.Keywords: transmission and distribution lines; erection process; erection method
中图分类号:TM726文献标识码:文章编号:
输配电线路的架设需要遵循一定的施工工序,讲求一定的方法,同时一些线路还增设了避雷装置。架空线路经常应用在输配电线架设线路,在架空线路中高压架空线通常采用的是裸导线,低压架空线通常采用的是绝缘导线。在架设的过程中要注意选择恰当的架设方法,遵循步骤,在架设之前需要明确电线的走向,进行勘察,然后在进行基础施工,最后保证导线连接的固定性。这些工序都需要按照科学合理的方法进行,下面本文就对实际架设的施工工序步骤和方法进行论述。
一 输配电线路架设施工勘测定位
输配电线路的架设施工需要遵循施工工序,当线路的走向明确之后,首先就需要对线路的沿途进行勘察,并且要做好勘察记录,以便为今后的架设施工打下基础。由于线路的铺设需要采用直线的走向,在这个过程中要尽量的避开跨越物,这就需要在勘察的过程中需要进行定位,确定好重要转角杆的具体位置,之后将每一个地方的杆型和杆距确定好,并且要在每个杆坑的位置打上木桩,标好标号,需要注意的是,在这个过程中还需要对各种拉线的形式作出标定。勘察定位能够准确的确定出电杆的位置,但是对于位置的精确度还需要再进行检查,没有误差之后再根据土质的实际情况确定好电线杆的坑形是采用什么形式,是圆形坑或者是梯形坑。如果说施工地的土质较为疏松,在施工时杆高在十米以上,适合挖三阶梯的坑形。如果说施工地的土质较硬,当杆高在十米以上的情况下,可以选用圆形坑,这样更有利于架设施工的顺利进行。综上所述,输配电线路架设时的勘察工作十分关键,其对于选择什么样的坑形起到关键作用。在勘察时需要掌握方法,选取恰当的勘察工具,认真做好记录,保证勘察数据的精确度。
二 电线杆的组装和立杆施工
输配电线路架设施工的第一步勘察工作完成之后,就需要对电线杆进行组装,方便今后的架设施工。对地面的杆顶支座、绝缘子以及横担进行组装和整体立杆,能够实现施工的便捷操作。对于三相三线的架空线路,在组装时需要保证三角形的排列组合,也可以采用水平的排列。在这个过程中需要注意,中性线的截面较小,而且其机械强度较差,所以在架设施工中需要保证导线处于电线杆的中间位置,需要保证中性线的架设位置不能够高于统一回路的相线,还需要實现内中性线排列组合的统一。在架设的过程中,对于同一级别的负荷供电双电源线路的架设,不能够使其在同一个电线杆上;对不同电压线路的同杆架设施工时,要保证电压值较高的线路在上面,较低的导线在下面的排列顺序。对于多回路导线同杆架设的过程中,需要采用混合排列或者是垂直排列的方式进行。在动力线和照明线的架设施工过程中,动力线需要排列在上面,而照明线需要排列在下面,低压线路上面的广播线路应在排列在最下面。
立杆的程序则是要将组装好的电线杆按照一定的程序、方向和位置,将其竖立起来,并且埋入到事先挖好的坑中,在这个过程中需要严格遵守施工程序和施工方法,必须要先立杆,立杆完成之后再对杆身进行调整,所有项目完成之后再做好填土夯实的工作。
三 输配电线路架设中拉放线施工
输配电线路架设中的拉线施工,通常情况下是在10KV以下的线路下进行的,对于线路有一定的要求,如果是铁线超过九股,就需要用钢绞线制作,如果采用直径是4毫米的镀锌铁线来制作导线的话,一般可以少于三股。在架设的过程中,要保证拉线的质量,其不能够出现接头,对于地面上下300毫米的拉线,则必须要涂抹防腐油,以保证拉线的防腐性能。还需要注意,拉线的防线一定要和不平衡力的方向相反,并且要保证拉线和电线杆之间的夹角为45度。
架设中放线的过程也需要严格按照施工工艺和施工要求进行,放线过程中线的盘孔内部要穿入轴扛,同时要将轴扛的两端放在放线架上面,同时对于放线架还需要调整,要保证其两端都要处于同一个高度,对线盘要实施脱离底面的工作。防线过程中要按照要求进行,钢芯铝线需要在每根电杆上的横担预定出三个开口滑轮设备的挂口,这样讲每根导线拉到电杆后面以后,需要用绳子将每根导线提升,使其能够嵌入到滑轮设备之中,这样就完成了放线施工。在放线的整个过程中,需要保证有施工信号的传递,在施工的过程中还需要增加监督人员和导线的管理人员,以减少安全事故和损伤的现象,尤其是当导线到穿越道路的过程中必须要有专门的人员进行施工监管和维护,防止出现线路悬空的现象,伤及他人。
四 输配电线路架设中导线的连接和固定施工
导线的连接和架设时输配电架设施工中的关键环节,在这个过程中需要按照要求和工序进行,并且要采取恰当的方法。导线连接时需要满足以下要求:第一,对于不同材料的导线连接施工,需要在电线杆上面的跳线内完成,严格禁止在连接的过程中出现绞的现象。对于每一根导线,在档距范围内只能够允许有一个接头,当避雷针的设置和导线的设置需要跨越建筑物或者是通信线、电力线、河流道路等的时候,需要有接头以保证顺利完成连接施工。第二,对于导线接头处的机械强度要求也较为严格,要保证其不能够比之前的导线低,接头处的电阻长度也不能够高于同长度的导线电阻的1.2倍。在导线连接的过程中可以采用另缠法,这样连接的导线电阻率较小,能够保证正常的接触能力。第三,在导线连接过程中,分支杆和耐张杆的跳连线,一定要采用T字形的线架已完成合并连接。除了上述的三点之外,在连接的过程中还需要讲究方式方法和施工设备的应用,根据施工作业的方式以及施工的设备,可以将输配电线路的连接方法分为三种,即爆压式连接方式、液压式连接方式以及钳压式连接方式,在实际的连接过程中要根据实际情况选用合适的方法。
需要注意的是,在紧线的过程中,要先将导线的一端固定在绝缘子上面,之后再将进线段内的导线都挂在绝缘子槽内,对于紧线器的尾绳,一定要绑在横担上,这样才能够固定住。
五 输配电线路安装完成之后的要求分析
当输配电线路完成安装之后,不能与所有的施工任务完成,为了保证线路运行的顺利和安全性,需要进行竣工验收检查,例如对于施工线路上电线杆的垂直问题要进行检查,要保证耐张段的电杆在一条直线上面,且线路的中心和横担之间也要保证垂直。对于导线的紧固、各种坑的填土是否符合要求等都要进行检查,以保证线路架设的安全性和实用性。除此之外还需要检查施工中使用的金属器具,看其是否符合设计的要求和施工的规定,对电线的电阻值是否超出规定的额度也要进行检验。当所有的环节验收完成之后还需要对线路进行绝缘测试,当一切检验正常之后才能够投入使用。
结束语:输配电线路的架设施工对于确保供电工作具有重要的作用,在架设的过程中需要遵循工程工序和施工方法,按照规定完成架设,本文就从五个方面对相应的工序和方法进行了论述,希望对今后的输配电线路架设施工有一定的帮助作用。
参考文献:
[1] 陈志华 输配电线路架设施工工序与方法分析 硅谷,2013年第01期
[2] 于洪卫 输配电线路架设施工工序与方法 科技风,2011年第02期
[3] 崔冰山 输配电线路架设施工工序与方法 北京电力高等专科学校学报(自然科学版),2012年第29期
[4] 黄宵宁 输配电线路施工技术 中国电力出版社,2007-10
[5] 戴仁发 输配电线路施工 中国电力出版社,2006-09
关键字:输配电线路;架设施工工序;架设方法
Abstract: The rapid economic development led to the progress of society, in the process of rapid development in the demand for electricity is also increasing, but the current transmission and distribution lines are not able to meet the demand, which required the installation of new lines, in order to improve transmission and distribution the line is in operation reliability and stability. In this paper, as a starting point, from the line erection processes and methods were discussed.Keywords: transmission and distribution lines; erection process; erection method
中图分类号:TM726文献标识码:文章编号:
输配电线路的架设需要遵循一定的施工工序,讲求一定的方法,同时一些线路还增设了避雷装置。架空线路经常应用在输配电线架设线路,在架空线路中高压架空线通常采用的是裸导线,低压架空线通常采用的是绝缘导线。在架设的过程中要注意选择恰当的架设方法,遵循步骤,在架设之前需要明确电线的走向,进行勘察,然后在进行基础施工,最后保证导线连接的固定性。这些工序都需要按照科学合理的方法进行,下面本文就对实际架设的施工工序步骤和方法进行论述。
一 输配电线路架设施工勘测定位
输配电线路的架设施工需要遵循施工工序,当线路的走向明确之后,首先就需要对线路的沿途进行勘察,并且要做好勘察记录,以便为今后的架设施工打下基础。由于线路的铺设需要采用直线的走向,在这个过程中要尽量的避开跨越物,这就需要在勘察的过程中需要进行定位,确定好重要转角杆的具体位置,之后将每一个地方的杆型和杆距确定好,并且要在每个杆坑的位置打上木桩,标好标号,需要注意的是,在这个过程中还需要对各种拉线的形式作出标定。勘察定位能够准确的确定出电杆的位置,但是对于位置的精确度还需要再进行检查,没有误差之后再根据土质的实际情况确定好电线杆的坑形是采用什么形式,是圆形坑或者是梯形坑。如果说施工地的土质较为疏松,在施工时杆高在十米以上,适合挖三阶梯的坑形。如果说施工地的土质较硬,当杆高在十米以上的情况下,可以选用圆形坑,这样更有利于架设施工的顺利进行。综上所述,输配电线路架设时的勘察工作十分关键,其对于选择什么样的坑形起到关键作用。在勘察时需要掌握方法,选取恰当的勘察工具,认真做好记录,保证勘察数据的精确度。
二 电线杆的组装和立杆施工
输配电线路架设施工的第一步勘察工作完成之后,就需要对电线杆进行组装,方便今后的架设施工。对地面的杆顶支座、绝缘子以及横担进行组装和整体立杆,能够实现施工的便捷操作。对于三相三线的架空线路,在组装时需要保证三角形的排列组合,也可以采用水平的排列。在这个过程中需要注意,中性线的截面较小,而且其机械强度较差,所以在架设施工中需要保证导线处于电线杆的中间位置,需要保证中性线的架设位置不能够高于统一回路的相线,还需要實现内中性线排列组合的统一。在架设的过程中,对于同一级别的负荷供电双电源线路的架设,不能够使其在同一个电线杆上;对不同电压线路的同杆架设施工时,要保证电压值较高的线路在上面,较低的导线在下面的排列顺序。对于多回路导线同杆架设的过程中,需要采用混合排列或者是垂直排列的方式进行。在动力线和照明线的架设施工过程中,动力线需要排列在上面,而照明线需要排列在下面,低压线路上面的广播线路应在排列在最下面。
立杆的程序则是要将组装好的电线杆按照一定的程序、方向和位置,将其竖立起来,并且埋入到事先挖好的坑中,在这个过程中需要严格遵守施工程序和施工方法,必须要先立杆,立杆完成之后再对杆身进行调整,所有项目完成之后再做好填土夯实的工作。
三 输配电线路架设中拉放线施工
输配电线路架设中的拉线施工,通常情况下是在10KV以下的线路下进行的,对于线路有一定的要求,如果是铁线超过九股,就需要用钢绞线制作,如果采用直径是4毫米的镀锌铁线来制作导线的话,一般可以少于三股。在架设的过程中,要保证拉线的质量,其不能够出现接头,对于地面上下300毫米的拉线,则必须要涂抹防腐油,以保证拉线的防腐性能。还需要注意,拉线的防线一定要和不平衡力的方向相反,并且要保证拉线和电线杆之间的夹角为45度。
架设中放线的过程也需要严格按照施工工艺和施工要求进行,放线过程中线的盘孔内部要穿入轴扛,同时要将轴扛的两端放在放线架上面,同时对于放线架还需要调整,要保证其两端都要处于同一个高度,对线盘要实施脱离底面的工作。防线过程中要按照要求进行,钢芯铝线需要在每根电杆上的横担预定出三个开口滑轮设备的挂口,这样讲每根导线拉到电杆后面以后,需要用绳子将每根导线提升,使其能够嵌入到滑轮设备之中,这样就完成了放线施工。在放线的整个过程中,需要保证有施工信号的传递,在施工的过程中还需要增加监督人员和导线的管理人员,以减少安全事故和损伤的现象,尤其是当导线到穿越道路的过程中必须要有专门的人员进行施工监管和维护,防止出现线路悬空的现象,伤及他人。
四 输配电线路架设中导线的连接和固定施工
导线的连接和架设时输配电架设施工中的关键环节,在这个过程中需要按照要求和工序进行,并且要采取恰当的方法。导线连接时需要满足以下要求:第一,对于不同材料的导线连接施工,需要在电线杆上面的跳线内完成,严格禁止在连接的过程中出现绞的现象。对于每一根导线,在档距范围内只能够允许有一个接头,当避雷针的设置和导线的设置需要跨越建筑物或者是通信线、电力线、河流道路等的时候,需要有接头以保证顺利完成连接施工。第二,对于导线接头处的机械强度要求也较为严格,要保证其不能够比之前的导线低,接头处的电阻长度也不能够高于同长度的导线电阻的1.2倍。在导线连接的过程中可以采用另缠法,这样连接的导线电阻率较小,能够保证正常的接触能力。第三,在导线连接过程中,分支杆和耐张杆的跳连线,一定要采用T字形的线架已完成合并连接。除了上述的三点之外,在连接的过程中还需要讲究方式方法和施工设备的应用,根据施工作业的方式以及施工的设备,可以将输配电线路的连接方法分为三种,即爆压式连接方式、液压式连接方式以及钳压式连接方式,在实际的连接过程中要根据实际情况选用合适的方法。
需要注意的是,在紧线的过程中,要先将导线的一端固定在绝缘子上面,之后再将进线段内的导线都挂在绝缘子槽内,对于紧线器的尾绳,一定要绑在横担上,这样才能够固定住。
五 输配电线路安装完成之后的要求分析
当输配电线路完成安装之后,不能与所有的施工任务完成,为了保证线路运行的顺利和安全性,需要进行竣工验收检查,例如对于施工线路上电线杆的垂直问题要进行检查,要保证耐张段的电杆在一条直线上面,且线路的中心和横担之间也要保证垂直。对于导线的紧固、各种坑的填土是否符合要求等都要进行检查,以保证线路架设的安全性和实用性。除此之外还需要检查施工中使用的金属器具,看其是否符合设计的要求和施工的规定,对电线的电阻值是否超出规定的额度也要进行检验。当所有的环节验收完成之后还需要对线路进行绝缘测试,当一切检验正常之后才能够投入使用。
结束语:输配电线路的架设施工对于确保供电工作具有重要的作用,在架设的过程中需要遵循工程工序和施工方法,按照规定完成架设,本文就从五个方面对相应的工序和方法进行了论述,希望对今后的输配电线路架设施工有一定的帮助作用。
参考文献:
[1] 陈志华 输配电线路架设施工工序与方法分析 硅谷,2013年第01期
[2] 于洪卫 输配电线路架设施工工序与方法 科技风,2011年第02期
[3] 崔冰山 输配电线路架设施工工序与方法 北京电力高等专科学校学报(自然科学版),2012年第29期
[4] 黄宵宁 输配电线路施工技术 中国电力出版社,2007-10
[5] 戴仁发 输配电线路施工 中国电力出版社,2006-09