沈阳玻璃厂熔窑冷修工程原提计划为45天,在部里讨论1958年生产计划时确定为38天,大跃进中,经工人和有关技术人员讨论,第一次提出缩短到35天,第二次改为32天,最后确定29天,实际只用了26天就修完了,创造了该厂熔窑冷修时间最新的历史记录.由于熔窑冷修时间的缩短,可增产玻璃4万箱. 这一成绩的取得,首先是经过整风、“双反”等运动,工人群众思想觉悟普遍提高,在生产大跃进的高潮中,劳动热情空前高涨.各级党、政领导又充分作好了政治思想工作.其次在组织工作和技术工作上,接受以往的经验教训,采取了一些新的措施: 一、施工、质量检查、安全工作全部交给修窑瓦
The original plans for the cold-refining of the melting furnaces in the Shenyang Glass Factory were 45 days. During the ministry’s discussion of the 1958 production plan, it was determined as 38 days. During the Great Leap Forward, the workers and relevant technical personnel discussed the first proposal to shorten it to 35 days. The second time was changed to 32 days and the final period was 29 days. It took only 26 days to complete the repair, which created the latest historical record of the time for the factory’s cold kiln repair. As the time for the cold kiln repair is shortened, the glass can be increased. Wan Wan. This achievement was first achieved through rectification, “double opposition” and other movements, and the ideological awareness of the working masses has generally improved. During the climax of the Great Leap Forward, labor enthusiasm has risen unprecedentedly. Party and government leaders at all levels have fully Good political and ideological work. Secondly, in organizational work and technical work, we accepted previous experiences and lessons and adopted some new measures: First, construction, quality inspection, and safety work were all handed over to the kiln.