摘要:混凝土是建筑行业施工常用的建筑材料,在使用过程中发挥着重要的性能作用。随着该材料广泛运用于民用建筑施工里,对混凝土的浇注施工加以研究有着重要的意义。本文以在工业与民用建筑施工过程中对混凝土的使用情况为引子针对混凝土浇筑过程中对模板、钢筋的要求以及混凝土的搅拌、浇、振捣,施工缝的留置,还有常见的梁、柱、板的浇筑,混凝土的养护等方面的问题展开论述;对极易出现疏忽及质量通病的地方进行重点论述;对个施工过程中的技术要求、施工工艺提出较详细的要求及保证措施。
关键词:建筑工程;混凝土施工;技术探讨
Abstract: The construction industry is the construction of concrete used in building material, plays an important role in the performance in the use process. As the material is widely used in civil construction, pouring construction of concrete study has important significance. In the industrial and civil construction process on the use of concrete for the primer according to the requirement of template, reinforcing bar in concrete pouring process and concrete mixing, pouring, vibrating, indwelling of construction joint, and common girders, columns, plate pouring, discusses the concrete curing and other aspects of the problem; discusses on prone to neglect and quality problems of a place; in the process of construction technical requirements, construction technology put forward detailed requirement and guarantee measures.
Key words: construction engineering; construction technology of concrete;
中圖分类号:TU74 文献标识码:文章编号:
一、混凝土浇筑施工技术
1、柱与墙混凝土浇筑技术柱与墙浇筑前,底部应填以5~10 cm厚的砂浆,同混凝土配合比。应分层振捣柱混凝土,每层厚度不要大于50 cm。插入式振捣棒使用时,不得触动钢筋和预埋件。不但上面要振捣实在,下面也要随时敲打敲实模板。若柱墙高超过3 m,必须采用串筒措施,或者在模板侧面开洞,以便安装溜槽实施分段浇筑。每段高度不要超过2 m,应在每段混凝土浇筑后,封实洞口模板,用柱箍箍牢。柱墙混凝土应一次浇筑成功。由于梁板混凝土强度等级与柱混凝土强度等级不同,所以,应在梁柱节点接头部位,其梁板混凝土要按柱子强度等级,浇筑和振捣混凝土,采用钢板网作临时隔断缝。浇筑完毕后,应随时将伸出的搭接钢筋整理到位。
2、梁与板混凝土浇筑技术
本工程梁与板混凝土浇筑将采用泵送的方法,将混凝土输送到应浇捣部位。同时采用“赶浆法”进行梁与板的浇筑,即先从一端开始浇筑梁,当到达板底时,再与板混凝土一起浇筑。注意梁柱节点钢筋较紧密,浇筑该处混凝土时,应采取小粒径石子的混凝土(同强度等级),并采用小直径振捣棒振捣振实。板混凝土虚铺厚度应比板厚稍微厚,用平板振捣器沿着浇筑的垂直方向,来回振捣振实。在浇筑板混凝土时,禁用振捣棒铺摊混凝土。楼板不能留缝隙,如果遇到特殊情况,需要保留缝隙,应该沿着次梁的方向进行楼板浇筑,施工缝不能留有斜槎,表面应与梁轴线或板面垂直,而且缝隙需要在次梁跨度的中间1/3内。施工缝处已浇筑混凝土的表面应凿毛,剔除浮动石子,用水冲干净。
3、楼梯混凝土浇筑
楼梯混凝土宜采用自下而上浇筑。先振实底板混凝土,到达踏步位置时,再与踏步混凝土一起浇捣,不断依次推进,并随时用木抹子抹平踏步表面。宜连续浇筑楼梯混凝土,多层楼梯施工缝应留在楼梯段1/3处,并垂直于梯板面。
二、多强度等级混凝土浇筑方案
当柱、核心筒墙混凝土强度等级高于梁、板混凝土强度等级不超过 2 级时(10MPa)可根据实际情况采用柱、核心筒墙混凝土随同梁、板一起浇注。但考虑到梁柱节点处的混凝土强度如果取用梁、板的混凝土强度,可能会引起柱在竖向荷载作用下的承载力不足,以及地震作用下节点核心区的抗剪承载力不足,可相应采用加插短筋(柱主筋数的 0~50%)的方法进行补强。整个方案应征得设计单位同意。当地下室外墙与梁板混凝土强度等级不同,柱和核心筒体与梁板混凝土强度等级不同, 级差大于 2 级以上时, 在柱、墙梁底向上10mm~15mm 处设置水平施工缝,柱、墙混凝土分两次浇筑。第一次先浇筑柱和核心简体混凝土到梁底面向上 15mm 处;第二次浇筑混凝土前,在梁柱核心简体距离柱边梁上设置钢丝网片,应在支梁侧模前做好此工作;浇筑不同强度等级混凝土的顺序为:先核心筒体区梁、柱、墙高强度等级混凝土,其次浇筑地下室外墙混凝土(分次浇筑),再浇筑梁、板混凝土(分次浇筑)。必须在梁柱节点高区混凝土和地下室外墙混凝土初凝前浇筑梁板混凝土。为避免梁、板低强度等级混凝土流入柱、核心筒墙高强度等级混凝土范围,以及防止高强度等级混凝土流淌过远,造成浪费。因此在施工过程中,在柱、核心筒墙、梁板节点处四周确定合适的距离(600mm)加设钢丝网。
三、混凝土浇筑方式及流程
混凝土的施工可根据一次浇注方量、浇注种类、混凝土供应情况、气温、机械及人员等情况,每个自然层采取分两次浇注或一次性浇注的方法。其具体方式及流程如下:
3.1 主体结构中每个自然层作为两个施工段:浇筑柱、核心筒墙混凝土(混凝土浇至梁底向上 15mm 处)→安装梁、模板,梁板钢筋工程+浇筑梁、板混凝土。
3.2 每个自然层作为一个施工段,即柱、核心筒墙、梁、板混凝土一次性浇筑。混凝土浇筑顺序:浇筑核心筒墙→浇筑柱混凝土→浇筑梁、板混凝土。
四、施工过程质量控制
4.1 确定各强度等级混凝土配合比
施工单位应提前对商品混凝土搅拌站试验室提出各种强度等级的混凝土技术指标(混凝土加缓凝剂,初凝时间不小于 8h 等)。同时应要求实验室考虑在满足强度等级及可泵性的条件下,对柱子混凝土,尽可能减少水泥用量、减少水灰比、减少含砂率、减少坍落度、增加石子含量,并对粉煤灰和外加剂的用量作相应的调整。商品混凝土搅拌站试验室按照相应技术要求进行试配制。试配后制作试块,测量坍落度、初凝时间、终凝时间,到 28 天进行强度试验。试验各项指标合格,开出各种配合比单经监理工程师确认后,按配合比投料搅拌混凝土。每次搅拌的混凝土要求沙、石料同一产地,水泥同一厂家同一批号,外加剂同一厂家生产的产品。
4.2 混凝土坍落度选择
在施工现场必须加强不同强度等级混凝土输送监督和调度工作。根据浇筑部位的不同选用不同强度等级及不同坍落度的混凝土,控制好浇筑进度,确保强度等级不同的混凝土在初凝前整体浇筑完毕。同时在现场,应对每车混凝土都进行坍落度检测。
4.3 混凝土的运输与浇注
混凝土运输应以最少的转载次数和最短时间,从搅拌地点运到浇筑地点。其混凝土的延续时间不宜超过相应的规定。作为拦截高强度等级混凝土的方式,钢丝网片的设置与梁板钢筋绑扎同时进行,位置位于在梁上距柱边距离 600mm 处,钢丝网片应绑扎牢固,能够抵抗混凝土浇注时的冲击力。浇筑时,先浇筑柱、核心筒墻的高强度等级混凝土区;后浇筑梁板低强度等级混凝土区,浇筑混凝土的原则允许高强度等级混凝土流至梁上距柱边距离 600mm,超过钢丝网片,不允许低强度等级混凝土流入柱、核心筒墙区。对少量通过网眼渗入梁底的冷浆要及时处理干净。当采用输送管输送混凝土时,应由远而近浇筑;同一层的混凝土,先竖向结构后水平结构的顺序,分层连续浇筑;当不允许留施工缝时,区域之间,上下层之间的混凝土浇筑停歇时问,不得超过混凝土初凝时间。
梁板的混凝土采用二次振捣法,即在混凝土初凝前再振捣一次,增强高低强度等级混凝土交接面的密实性,减少收缩。混凝土自吊斗口下落的自由倾落高度不宜超过 2m。梁、板应同时浇筑,浇筑方法应由一端开始用“赶浆法”即先浇筑梁,根据梁高分层阶梯形浇筑。当达到板底位置时再与板的混凝土一起浇筑,随着阶梯形不断延伸,梁板混凝土浇筑连续向前推进。和板连成整体高度大于 1m 的梁,允许单独浇筑。浇筑时,浇筑与振捣必须紧密配合,第一层下料慢些,梁底混凝土充分振实后再下二层料。用“赶浆法”保持水泥浆沿梁底包裹石子向前推进,每层均应振实后下料,梁底及梁帮部位应振实,振捣时不得触动钢筋及预埋件。梁,柱节点钢筋较密时,浇筑此混凝土时,宜用小粒径石子同强度等级的混凝土浇筑,并用小直径振捣棒振捣。
4.4 混凝土养护
混凝土养护应及时,使其不会因温差和强度等级不同而产生收缩裂缝。浇水次数以能使混凝土面层保持湿润状态为准,特别是梁。除了板面浇水外;还应在板下梁侧浇水养护,并尽可能推迟梁侧模的拆模时间。防水抗渗混凝土养护期不少于 14天;一般混凝土养护不少于 7天;后浇带混凝土养护不少于 28 天。
五、结语
目前,随着建筑工程结构的发展,对混凝土的施工技术要求大大提高了。高层建筑施工过程混凝土工程质量的控制措施包括施工过程中的工序质量控制、工程项目施工中的技术复合制度、质量控制点的设立和工程质量的预控。混凝土施工在建筑工程施工过程中是一个重要的步骤,特别是在高层建筑不断发展的今天,混凝土施工技术就更为重要,只有控制好混凝土施工技术,才能有效保证工程质量。
关键词:建筑工程;混凝土施工;技术探讨
Abstract: The construction industry is the construction of concrete used in building material, plays an important role in the performance in the use process. As the material is widely used in civil construction, pouring construction of concrete study has important significance. In the industrial and civil construction process on the use of concrete for the primer according to the requirement of template, reinforcing bar in concrete pouring process and concrete mixing, pouring, vibrating, indwelling of construction joint, and common girders, columns, plate pouring, discusses the concrete curing and other aspects of the problem; discusses on prone to neglect and quality problems of a place; in the process of construction technical requirements, construction technology put forward detailed requirement and guarantee measures.
Key words: construction engineering; construction technology of concrete;
中圖分类号:TU74 文献标识码:文章编号:
一、混凝土浇筑施工技术
1、柱与墙混凝土浇筑技术柱与墙浇筑前,底部应填以5~10 cm厚的砂浆,同混凝土配合比。应分层振捣柱混凝土,每层厚度不要大于50 cm。插入式振捣棒使用时,不得触动钢筋和预埋件。不但上面要振捣实在,下面也要随时敲打敲实模板。若柱墙高超过3 m,必须采用串筒措施,或者在模板侧面开洞,以便安装溜槽实施分段浇筑。每段高度不要超过2 m,应在每段混凝土浇筑后,封实洞口模板,用柱箍箍牢。柱墙混凝土应一次浇筑成功。由于梁板混凝土强度等级与柱混凝土强度等级不同,所以,应在梁柱节点接头部位,其梁板混凝土要按柱子强度等级,浇筑和振捣混凝土,采用钢板网作临时隔断缝。浇筑完毕后,应随时将伸出的搭接钢筋整理到位。
2、梁与板混凝土浇筑技术
本工程梁与板混凝土浇筑将采用泵送的方法,将混凝土输送到应浇捣部位。同时采用“赶浆法”进行梁与板的浇筑,即先从一端开始浇筑梁,当到达板底时,再与板混凝土一起浇筑。注意梁柱节点钢筋较紧密,浇筑该处混凝土时,应采取小粒径石子的混凝土(同强度等级),并采用小直径振捣棒振捣振实。板混凝土虚铺厚度应比板厚稍微厚,用平板振捣器沿着浇筑的垂直方向,来回振捣振实。在浇筑板混凝土时,禁用振捣棒铺摊混凝土。楼板不能留缝隙,如果遇到特殊情况,需要保留缝隙,应该沿着次梁的方向进行楼板浇筑,施工缝不能留有斜槎,表面应与梁轴线或板面垂直,而且缝隙需要在次梁跨度的中间1/3内。施工缝处已浇筑混凝土的表面应凿毛,剔除浮动石子,用水冲干净。
3、楼梯混凝土浇筑
楼梯混凝土宜采用自下而上浇筑。先振实底板混凝土,到达踏步位置时,再与踏步混凝土一起浇捣,不断依次推进,并随时用木抹子抹平踏步表面。宜连续浇筑楼梯混凝土,多层楼梯施工缝应留在楼梯段1/3处,并垂直于梯板面。
二、多强度等级混凝土浇筑方案
当柱、核心筒墙混凝土强度等级高于梁、板混凝土强度等级不超过 2 级时(10MPa)可根据实际情况采用柱、核心筒墙混凝土随同梁、板一起浇注。但考虑到梁柱节点处的混凝土强度如果取用梁、板的混凝土强度,可能会引起柱在竖向荷载作用下的承载力不足,以及地震作用下节点核心区的抗剪承载力不足,可相应采用加插短筋(柱主筋数的 0~50%)的方法进行补强。整个方案应征得设计单位同意。当地下室外墙与梁板混凝土强度等级不同,柱和核心筒体与梁板混凝土强度等级不同, 级差大于 2 级以上时, 在柱、墙梁底向上10mm~15mm 处设置水平施工缝,柱、墙混凝土分两次浇筑。第一次先浇筑柱和核心简体混凝土到梁底面向上 15mm 处;第二次浇筑混凝土前,在梁柱核心简体距离柱边梁上设置钢丝网片,应在支梁侧模前做好此工作;浇筑不同强度等级混凝土的顺序为:先核心筒体区梁、柱、墙高强度等级混凝土,其次浇筑地下室外墙混凝土(分次浇筑),再浇筑梁、板混凝土(分次浇筑)。必须在梁柱节点高区混凝土和地下室外墙混凝土初凝前浇筑梁板混凝土。为避免梁、板低强度等级混凝土流入柱、核心筒墙高强度等级混凝土范围,以及防止高强度等级混凝土流淌过远,造成浪费。因此在施工过程中,在柱、核心筒墙、梁板节点处四周确定合适的距离(600mm)加设钢丝网。
三、混凝土浇筑方式及流程
混凝土的施工可根据一次浇注方量、浇注种类、混凝土供应情况、气温、机械及人员等情况,每个自然层采取分两次浇注或一次性浇注的方法。其具体方式及流程如下:
3.1 主体结构中每个自然层作为两个施工段:浇筑柱、核心筒墙混凝土(混凝土浇至梁底向上 15mm 处)→安装梁、模板,梁板钢筋工程+浇筑梁、板混凝土。
3.2 每个自然层作为一个施工段,即柱、核心筒墙、梁、板混凝土一次性浇筑。混凝土浇筑顺序:浇筑核心筒墙→浇筑柱混凝土→浇筑梁、板混凝土。
四、施工过程质量控制
4.1 确定各强度等级混凝土配合比
施工单位应提前对商品混凝土搅拌站试验室提出各种强度等级的混凝土技术指标(混凝土加缓凝剂,初凝时间不小于 8h 等)。同时应要求实验室考虑在满足强度等级及可泵性的条件下,对柱子混凝土,尽可能减少水泥用量、减少水灰比、减少含砂率、减少坍落度、增加石子含量,并对粉煤灰和外加剂的用量作相应的调整。商品混凝土搅拌站试验室按照相应技术要求进行试配制。试配后制作试块,测量坍落度、初凝时间、终凝时间,到 28 天进行强度试验。试验各项指标合格,开出各种配合比单经监理工程师确认后,按配合比投料搅拌混凝土。每次搅拌的混凝土要求沙、石料同一产地,水泥同一厂家同一批号,外加剂同一厂家生产的产品。
4.2 混凝土坍落度选择
在施工现场必须加强不同强度等级混凝土输送监督和调度工作。根据浇筑部位的不同选用不同强度等级及不同坍落度的混凝土,控制好浇筑进度,确保强度等级不同的混凝土在初凝前整体浇筑完毕。同时在现场,应对每车混凝土都进行坍落度检测。
4.3 混凝土的运输与浇注
混凝土运输应以最少的转载次数和最短时间,从搅拌地点运到浇筑地点。其混凝土的延续时间不宜超过相应的规定。作为拦截高强度等级混凝土的方式,钢丝网片的设置与梁板钢筋绑扎同时进行,位置位于在梁上距柱边距离 600mm 处,钢丝网片应绑扎牢固,能够抵抗混凝土浇注时的冲击力。浇筑时,先浇筑柱、核心筒墻的高强度等级混凝土区;后浇筑梁板低强度等级混凝土区,浇筑混凝土的原则允许高强度等级混凝土流至梁上距柱边距离 600mm,超过钢丝网片,不允许低强度等级混凝土流入柱、核心筒墙区。对少量通过网眼渗入梁底的冷浆要及时处理干净。当采用输送管输送混凝土时,应由远而近浇筑;同一层的混凝土,先竖向结构后水平结构的顺序,分层连续浇筑;当不允许留施工缝时,区域之间,上下层之间的混凝土浇筑停歇时问,不得超过混凝土初凝时间。
梁板的混凝土采用二次振捣法,即在混凝土初凝前再振捣一次,增强高低强度等级混凝土交接面的密实性,减少收缩。混凝土自吊斗口下落的自由倾落高度不宜超过 2m。梁、板应同时浇筑,浇筑方法应由一端开始用“赶浆法”即先浇筑梁,根据梁高分层阶梯形浇筑。当达到板底位置时再与板的混凝土一起浇筑,随着阶梯形不断延伸,梁板混凝土浇筑连续向前推进。和板连成整体高度大于 1m 的梁,允许单独浇筑。浇筑时,浇筑与振捣必须紧密配合,第一层下料慢些,梁底混凝土充分振实后再下二层料。用“赶浆法”保持水泥浆沿梁底包裹石子向前推进,每层均应振实后下料,梁底及梁帮部位应振实,振捣时不得触动钢筋及预埋件。梁,柱节点钢筋较密时,浇筑此混凝土时,宜用小粒径石子同强度等级的混凝土浇筑,并用小直径振捣棒振捣。
4.4 混凝土养护
混凝土养护应及时,使其不会因温差和强度等级不同而产生收缩裂缝。浇水次数以能使混凝土面层保持湿润状态为准,特别是梁。除了板面浇水外;还应在板下梁侧浇水养护,并尽可能推迟梁侧模的拆模时间。防水抗渗混凝土养护期不少于 14天;一般混凝土养护不少于 7天;后浇带混凝土养护不少于 28 天。
五、结语
目前,随着建筑工程结构的发展,对混凝土的施工技术要求大大提高了。高层建筑施工过程混凝土工程质量的控制措施包括施工过程中的工序质量控制、工程项目施工中的技术复合制度、质量控制点的设立和工程质量的预控。混凝土施工在建筑工程施工过程中是一个重要的步骤,特别是在高层建筑不断发展的今天,混凝土施工技术就更为重要,只有控制好混凝土施工技术,才能有效保证工程质量。