我厂共安装SZP-6.5/13型锅炉三台,年耗蒸汽6×10~4t。厂内热网敷设型式:不通行地沟二千余米,架空敷设一千余米。锅炉冬季运行二台,夏季运行一台,基本满足了生产、生活的用汽需要。近年来,为适应“保军转民”战略任务的需要,原军用品生产线不断地被改建,用能设备的容量、数量和位置亦随之在变,造成了热网运行工况的不断恶化,致使能源浪费十分严重。其表现在以下三个方面:
Our factory has installed three SZP-6.5/13 boilers and consume 6×10~4t of steam each year. The type of thermal network laid in the factory: There are no more than two thousand meters of trenches, and more than a thousand meters of overhead lines are laid. The boiler operates two sets in winter and one in summer, which basically meets the need for steam for production and living. In recent years, in order to meet the needs of the strategic mission of “maintaining military support and transferring people,” the original military product production line has been continuously reconstructed, and the capacity, quantity, and location of energy-consuming equipment have also changed, resulting in the continuous deterioration of operating conditions of heating networks. , resulting in very serious energy waste. Its performance in the following three aspects: