【西德《原子经济新闻》1985年6月号第1页报道】西德快堆核电站建造公司宣布,SNR-300原型快堆核电站的现场建造与组装工作已结束。钠冷却剂已于1985年4月底到5月初注入反应堆容器和钠主回路系统,系统泵也已调试。主冷却回路与冷却塔的试验工作也已同时完成。装料工作计划在1985年末和1986年初进行,在此之前将进行各个系统部件与各种安全设备的总体运行试验。
[Atomic Economic News, West Germany, June 1985, p. 1] West Germany Fast Reactor Nuclear Power Plant Construction Company announced that the on-site construction and assembly of the SNR-300 prototype fast reactor nuclear power plant has been completed. The sodium coolant was injected into the reactor vessel and the sodium main loop system from the end of April 1985 to the beginning of May 1985, and the system pump was also commissioned. The test work of the main cooling circuit and the cooling tower has also been completed at the same time. The loading work plan was carried out in late 1985 and early 1986. Prior to this, the overall operational tests of various system components and various safety devices will be conducted.