论文部分内容阅读
[案件简介]2004年2月,A公司受让了B公司位于深圳市龙岗镇一块地的土地使用权,拟建设科技园。同年3月,A公司取得深圳市规划与国土资源局核发的房地产证,随即向主管部门申办各项用地规划手续和施工建设手续,着手科技园的建设。期间,A公司先后取得行政主管部门核发《建设用地规划许可证》、
[Case Introduction] In February 2004, Company A acquired the land use rights of Company B in a piece of land in Longgang Town, Shenzhen City, and planned to build a science park. In March of the same year, Company A obtained the real estate certificate issued by Shenzhen Planning and Land Resources Bureau and immediately applied to the competent department for the formalities of land use planning and construction construction procedures and proceeded to the construction of science and technology parks. During the period, Company A has successively obtained the “Construction Land Planning Permit” issued by the administrative department in charge,