发表《我对宝钢三期工程几个问题的回忆》后,有些同志提出了些意见,我想有必要作一点补充。一、关于三期工程投资问题有人认为,与国外企业或者宝钢一、二期比较,宝钢三期工程投资太高了。宝钢三期概算总投资为623亿人民币,施工过程中物价稳定,扣除涨价预备金以及汇率、税
After publishing “My Memories on Several Issues of Baosteel’s Third-phase Project”, some comrades put forward some opinions, and I think it is necessary to add something. I. Regarding the investment in the third phase of the project Some people think that compared with foreign companies or Baosteel’s Phase I and II, Baosteel’s investment in the third phase of the project is too high. The estimated total investment of Baosteel’s third phase is RMB 62.3 billion. The price of construction is stable during the construction process. Deductions for reserve prices and exchange rates, taxes