尧化门编组站工程位于丘陵起伏地带,站埸土方平整后,由于铁路生产业务的特点,一些房屋必需建造于一定的位置,难以避开高填土地带,个别房屋又需紧靠铁路建筑限界,要求具备稳定性的条件。为此,如何处理好高填土上建筑物既坚固稳定又减少建造费用,成为一个重要课题。我们在这项工作中采用过一些办法,解决了一些问题,下面重点介绍一下我们的实践和体会。一、本地区填土的基本情况 1.在一大片平原上普遍填高6~7m。 2.在陡坡上或在原铁路线路堤坡上帮
Due to the characteristics of the railway production business, some houses must be built in a certain position, so it is difficult to avoid the high-filled land. Some houses also need to be close to the boundary of railway construction , Requires the conditions for stability. To this end, how to deal with the high fill of the building is both solid and stable and reduce the cost of construction has become an important issue. We have taken some measures in this work to solve some problems. The following highlights our practices and experiences. First, the basic situation of filling the area 1. In a large plain generally filled 6 ~ 7m. 2. On the steep slope or in the original railway embankment slope to help