结合南水北调中线工程建设管理制度和工程建设实际,焦作段建设管理处制订了一系列工程变更管理办法,明确了工程变更的分类,完善了工程变更申请、审批、审核和结算程序,加强建立工程变更台账管理,明确了焦作段建管处的职责和权限,不仅提高了焦作2段工程合同管理水平,同时为南水北调工程建设管理工作提供了宝贵经验。
Combined with the construction management system of mid-route of South-to-North Water Diversion Project and the actual construction of the project, Jiaozuo Section Construction Management Office has formulated a series of engineering change management measures, clarified the classification of project changes, improved the application procedures for project change approval, audit and settlement, and strengthened the establishment of engineering changes The management of account receivables clearly defined the responsibilities and authorities of Jiaozuo Duanjian Pipe Department, which not only improved the contract management level of the second-stage Jiaozuo project, but also provided valuable experience for the construction management of the South-to-North Water Diversion Project.