港沟白云岩矿区1960年2月8日投入勘探,经6天时间结束了野外工作,4天时间完成了室内整理和总结报告工作,于18日上午向省局提出了勘探总结报告,前后历时共十天。投入勘探施工和室内总结的人数为37人,其中地质5人、槽探13人、测量6人、化验、岩矿8人、绘图5人。共计完成工作量1:2000地质测量0.8平方公里,1:50000区域地质测量110平方公里,实测地质剖面2500米,取
The Ganggou dolomite mining area was put into exploration on February 8, 1960. After 6 days, it ended its field work. It completed indoor finishing and summary report work within 4 days. On the morning of the 18th, it submitted a summary report of exploration to the provincial bureau. A total of ten days. The number of people involved in exploration construction and indoor summaries was 37, including 5 geologists, 13 trench explorers, 6 surveyors, 8 labs, 8 rock mines, and 5 plots. Totally completed workload 1:2000 geological survey 0.8 square kilometers, 1:50000 regional geological survey 110 square kilometers, measured geological profile 2500 meters, take