加气混凝土制品的形成,其中一个重要的环节是蒸养过程,在蒸养过程中,对温度(在高压釜中温度是以对应的压力来检测和度量的,恒温时是183℃,对应的压力是10Kg,所以,一般蒸养也叫升压,为了控制准确,以下只对压力进行调整和控制)的要求是有一定时间限制的,两个参数必须具备,如在一个小时中要升压3Kg,三个小时后即应达到10Kg,升压太快,会使坯体出现裂纹。升压太慢,又使成品强度不合格,以往由于人工手动进行控制,难以达到要求,为此,安装了一套养护自动控制系统。分述如下:
The formation of aerated concrete products, one of the most important part is the steam curing process, in the steam curing process, the temperature (in the autoclave temperature is measured and measured at the corresponding pressure, constant temperature is 183 ℃, the corresponding The pressure is 10Kg, so the general steam curing is also called boost, in order to control the accuracy of the following only to adjust and control the pressure) is a certain time limit the requirements of the two parameters must have, such as in an hour to boost 3Kg, after three hours should reach 10Kg, boost too fast, will make the body cracks. Boosting too slow, but also the finished product unqualified strength, because manual control in the past, it is difficult to meet the requirements, for which, installed a set of automatic control system. As follows: