一、前言 水电部《小水电建设与管理办法》中指出“一般应根据予测的需电量,用电力电量平衡法确定电站的规模,不得任意加大装机容量”。《小型水力发电站设计规范》第2.3.3条水电站的装机容量、工作容量及备用容量,可通过电力电量平衡、经技术经济比较和综合分析确定。以上“办法”和“规范”是我们小水电建设和管理的法规,作为水利水电建设者必须遵循的。本文的用意是按上述的法规,通过我省10个农村电气化试点县的装机容量状况,从电力电量平衡角度分析10个试点县在设计水平年的装机容
I. Preface The Ministry of Water and Electricity’s “Measures for the Construction and Management of Small Hydropower” states: “Generally, the scale of power plants should be determined according to the power demand to be measured and the power plant capacity balance method should be adopted, and the installed capacity should not be arbitrarily increased.” Article 2.3.3 of “Code for Design of Small-Scale Hydropower Stations” The installed capacity, working capacity and reserve capacity of hydropower stations can be determined through technical and economic comparison and comprehensive analysis through the balance of power and power. The above “measures” and “norms” are the laws and regulations for the construction and management of small hydropower. They must be followed by water conservancy and hydropower builders. The purpose of this article is based on the above laws and regulations, through the province’s 10 rural electrification pilot counties installed capacity status, from the perspective of power balance analysis of 10 pilot counties in the design level of installed capacity