引黄灌溉济卫工程,於一九五一年三月局部开工,同年九月全面開工,至十二月中旬,完成总幹渠及西灌区、东一灌区、斗渠以上建築物及农渠以上渠道。一九五二年二月完成毛渠及斗渠節制閘以下建築物,三月十二日第一期工程完工、並进行試水。这一伟大的工程,能於很短時间内勝利完成,除了黄河水利委员会的正确领导、該工程处全体员工及參加工作的广大群眾的积極努力工作等原因而外,該工程處在施工中所採用的工程负责制及开挖
The Yellow River Irrigation Project was partially started in March 1951 and completed in September of the same year. By mid-December, the completion of the main canal and the West Irrigation District, the Dongyi Irrigation District, the structures above the canal ditches, and the channels above the agricultural channels have been completed. . In February 1952, the following buildings under the control channel for the gross canal and the canal were completed. The first phase of the project was completed on March 12 and the water was tested. This great project can be completed successfully in a short time. Apart from the correct leadership of the Yellow River Conservancy Commission, the work of the entire staff of the Agency and the active work of the broad masses of people participating in the work, the Agency is working on The engineering responsibility system and excavation