论文部分内容阅读
第一章总则第1条本规范适用于炼油、化工装置基本建设中仪表和自动控制装置的施工及验收。第2条仪表的安装与调校应符合设计要求,如有修改,须经设计或有关单位的同意。第二章取源部件的位置装确定与安装第一节一般规定第3条取源部件(短管、管件、加工件等)和阀门的型号、规格、材质、加工精度等,应符合设计规定,并应具有检验合格证。
Chapter I General Provisions Article 1 This standard is applicable to the construction and acceptance of instruments and automatic control devices in the basic construction of oil refining and chemical plant. Article 2 The installation and adjustment of instruments shall comply with the design requirements and any modifications shall be subject to the design or the consent of the relevant organizations. Chapter II Determination of the location of the source components installed and installed the first section of the general provisions Article 3 take the source components (spools, fittings, machining parts, etc.) and the valve type, size, material, machining accuracy, etc., should meet the design requirements , And should have inspection certificate.