客车在工厂检修过程中,外墙板油漆(包括涂刮腻子及喷表面漆)周期约占客车检修总周期的38.8%(大中修客车检修总周期平均按18天计,油漆则为7天)。而其中油漆(包括腻子)的干燥时间为总周期的22%左右(约需96小时)。目前工厂在实际生产过程中,由于受到现有生产台位检修周期的限制,不得不将大部份油漆作业与车间其他工序平行进行。油漆作业没有一个清净
During the overhaul of the passenger car in the factory, the period of external wall board paint (including coated putty and spray paint) accounts for about 38.8% of the total maintenance cycle of the passenger vehicle (the average maintenance cycle of large and medium-sized passenger vehicles is 18 days on average and the paint is 7 days ). The drying time of paint (including putty) is about 22% of the total cycle (about 96 hours). At present, in the actual production process, the factory has to carry out most of its paint operations in parallel with other processes in the workshop due to the limitation of the current production stage maintenance cycle. Paint job without a clean