摘要:随着经济的快速发展,电力工程也有了较快的发展,由于电力工程项目的投资额度巨大、施工周期较长,施工过程复杂等一系列的特点,使得电力工程造价管理工作开展的意义更为重要。文章中笔者结合110KV电力工程的造价管理过程进行研究,对电力工程造价中的合同管理、成本控制以及线路的造价控制对110KV的电力工程造价进行探讨。
关键词;110KV;合同管理;成本控制;线路造价控制
Abstract: With the rapid economic development, electric power project also has a faster development, because the electric power engineering project the tremendous amount of investment, long construction period, the construction process is complex and a series of characteristics, which makes management of electric power engineering cost to carry out the significance of the more important. In this paper, combined with cost management process of 110KV power engineering research, the electric power engineering cost in contract management, cost control and cost control circuit of electric power engineering cost of 110KV is discussed.
Keywords: 110KV; contract management; cost control; project cost control
中图分类号:TU723.3文献标识码:文章编号:
随着科学技术的不断发展,35KV的变电站已经无法满足当代社会的需求,文章中笔者结合多年的工作情况,对110KV变电站的造价管理进行简要的介绍。为了有效的控制电力工程的造价管理,笔者从合同管理、线路的造价控制以及成本控制等方面进行了简要的介绍。随着电力行业的迅猛发展,电力工程规模的不断扩大,以及市场经济环境对施工材料价格的影响等一系列的因素使得电力工程的造价管理在建设项目施工过程中所发挥的作用更加明显。电力施工单位为了提高企业的竞争力,提高经济效益就必须做好电力工程的造价管理工作。只有这样才能保证施工单位的可持续发展,实现电力施工企业的长足发展。
工程造价在电力工程建设过程中的重要意义。
随着社会的快速发展,市场经济体制的不断发展,电力行业也有了较大的发展,为了提高电力施工企业的经济效益,提高其行业竞争力,施工企业也愈发重视工程造价管理工作。电力行业的有序发展是维持其他行业高速发展的支柱行业,为了保证电力施工的快速发展,施工单位应该根据电力施工的特点,对施工过程中的材料、机械、人工等成本进行有效的控制,除了进行成本控制之外,还应该加强施工过程中的合同管理以及线路造价管理。
110KV电力工程造价控制旨在降低工程的总造价,提高施工企业的经济效益,对电力企业的长足发展有着极为重要的意义。
合同管理在电力工程造价管理中的应用。
110KV电力施工过程中为了有效的控制工程造价就必须做好合同管理。进行合同管理是为了有效的约束建设单位以及施工单位的行为,将双方的责任和义务进行明确地划分。为了有效的控制工程造价需要对建设项目中对工程造价造成影响的因素进行有效的控制,在合同中做好明确地规定。由于电力施工过程中会出现许多可预测以及不可预测的变动,所以应该在合同中对这些变动进行详细的说明,避免之后合同双方出现双扯皮现象。
在电力项目施工合同的拟定过程中,业主为了维护自身的经济利益,在制定招标文件以及施工合同的同时会将一些不利因素隐含到合同当中。由于施工单位在进行谈判时通常会受到业主方的限制,承担较大的风险因素,施工单位在签订施工合同时应该对合同中的条例进行详细的分析,并正确分析业主的意图,只有做到知己知彼,在施工过程中才能有效的避免风险因素,做到百战百胜。
在电力工程施工过程中材料费以及设备费用占工程造价的百分之六十以上,所以在合同管理阶段要加强对设备、材料费用的管理。施工过程中工程进度款的支付是以施工合同为依据。在电力施工过程中经常出现设计变更的现象,而合同则是控制合同变更的依据。进行设计变更之后,必须做好签证工作,按照合同规定进行价款的调整,有效避免竣工阶段出现双扯皮现象。
合同管理是进行工程索赔的依据。在进行造价管理的过程中,应该加强索赔的主动性,根据合同条款以及相关规定对费用索赔以及工期索赔进行合理的控制。在进行工期索赔时,应该认证分析是否是关键工序的延误来判断是否进行工期索赔,并分析造成工期延误的原因,来划分双方的责任。竣工过程中根据承包合同、设计变更以及签证、造价相关的会议记录等方面的内容为依据作为竣工阶段索赔的依据。
三、电力线路造价控制
为了有效的控制工程造价应该从变电站的厂址选择,线路选择等方面来进行造价管理。应该选择线路长度较短、曲折系数较小。施工难度较低的路径。并且有合理规划和选择塔形以及桿塔基础,进而保证工程造价管理工作的顺利开展。
3.1、合理优化线路是控制电力工程造价的有效手段。
电力工程施工过程中降低工程造价最直接有效的方式就是对输电线路进行优化和设计。选择合理的路径是做好造价管理的重要手段。为了保证电力工程造价管理工作的顺利开展,在项目设计过程中,应该严格按照线路所处环境的实际地质、交通、气候条件对线路进行合理的优化设计。在进行线路优化的过程中应该充分考虑到施工的难易程度、造价控制以及安全等方面的内容,并且要保证对通信、军事设备的避让。而不是一味的追求输电线路的最短化。
3.2、选择合适的地线、导线是控制电力工程造价的有效手段。
实际施工过程中在进行地线以及导线的选择过程中,应综合考虑导线制造、线路的输送目的地负荷容量及负荷增长情况、运行维护等一些列的因素,进行合理的分析以及经济比较。保证导线和地线在发挥其设计性能的同时,有效的降低工程成本,来保证造价管理工作的顺利开展。
3.3、选择合适的塔形是控制电力工程造价的有效手段。
众所周知,在进行电力线路的优化过程中,塔形的规划和选择是极为重要的。选择合适的塔形可以有效的降低塔材的使用量,进而降低工程造价。在进行塔形的规划时,应该综合占地面积、工程造价、运输以及安全等各方面的因素,进行综合的分析和判断。在设计阶段应该根据施工实际情况进行他性的选择,在保证功能的同时,提高直型塔的使用量,最大限度降低线路的曲折系数,选择耗材量小的杆型。除此之外,还可以使用双回路以及多回路铁塔等来进行线路的规划,进而合理的控制工程造价。
3.4、合理的优化杆塔基础是控制电力工程造价的有效手段
在电力工程施工过程中,杆塔的基础时输电线路的重要组成部分,并且杆塔基础的施工占据了整个电力线路施工周期的一半时间。对整个电力工程的施工进度以及工程造价都有着极为重要的影响。为了实行配电线路的合理规划,有效的进行造价控制,就必须合理规划杆塔基础。
四、成本控制是进行造价管理的必要手段。
为了提高施工企业的行业竞争力,提高经济效益,施工单位要做好成本控制。在施工过程中制定合理的计划来有效地降低工程成本。这就要求施工单位从组织方面和技术方面双管齐下,来降低工程成本。施工单位可以使用先进的机械设备和施工工艺技术,来提高工作效率,降低工程成本。
在对工程成本进行管理的过程中应本着全面控制的原则进行管理。这就要求对施工单位的全企业、全部施工人员以及施工全过程进行控制。
为了提高施工企业的行业竞争力,提高经济效益,施工单位要做好成本控制。在施工过程中制定合理的计划来有效地降低工程成本。这就要求施工单位从组织方面和技术方面双管齐下,来降低工程成本。施工单位可以使用先进的机械设备和施工工艺技术,来提高工作效率,降低工程成本。
结束语:随着电力行业的发展,施工单位为了提高经济效益,增强行业竞争力就必须加强对电力施工过程中的造价管理。文章中笔者结合110KV输电线路的规划,从合同管理以及成本控制等方面对电力工程的工程造价管理进行研究。使得电力施工过程在保证工程质量的同时,来进一步提高经济效益促进电力行业的长足发展。
参考文献:
[1]电力建设工程预算定额第四册送电线路工程(2006年版)[S].北京:中国电力出版社,2007.
[2]徐春凤.电力施工企业工程造价管理中存在的问题及改善对策[J].电力科技,2012
[3]颜柬华.浅谈电力施工企业工程造价管理[J].工程管理,201
[4]. 李铁国.浅谈电力工程的造价管理与控制措施[J].科技资讯.2007(36)
关键词;110KV;合同管理;成本控制;线路造价控制
Abstract: With the rapid economic development, electric power project also has a faster development, because the electric power engineering project the tremendous amount of investment, long construction period, the construction process is complex and a series of characteristics, which makes management of electric power engineering cost to carry out the significance of the more important. In this paper, combined with cost management process of 110KV power engineering research, the electric power engineering cost in contract management, cost control and cost control circuit of electric power engineering cost of 110KV is discussed.
Keywords: 110KV; contract management; cost control; project cost control
中图分类号:TU723.3文献标识码:文章编号:
随着科学技术的不断发展,35KV的变电站已经无法满足当代社会的需求,文章中笔者结合多年的工作情况,对110KV变电站的造价管理进行简要的介绍。为了有效的控制电力工程的造价管理,笔者从合同管理、线路的造价控制以及成本控制等方面进行了简要的介绍。随着电力行业的迅猛发展,电力工程规模的不断扩大,以及市场经济环境对施工材料价格的影响等一系列的因素使得电力工程的造价管理在建设项目施工过程中所发挥的作用更加明显。电力施工单位为了提高企业的竞争力,提高经济效益就必须做好电力工程的造价管理工作。只有这样才能保证施工单位的可持续发展,实现电力施工企业的长足发展。
工程造价在电力工程建设过程中的重要意义。
随着社会的快速发展,市场经济体制的不断发展,电力行业也有了较大的发展,为了提高电力施工企业的经济效益,提高其行业竞争力,施工企业也愈发重视工程造价管理工作。电力行业的有序发展是维持其他行业高速发展的支柱行业,为了保证电力施工的快速发展,施工单位应该根据电力施工的特点,对施工过程中的材料、机械、人工等成本进行有效的控制,除了进行成本控制之外,还应该加强施工过程中的合同管理以及线路造价管理。
110KV电力工程造价控制旨在降低工程的总造价,提高施工企业的经济效益,对电力企业的长足发展有着极为重要的意义。
合同管理在电力工程造价管理中的应用。
110KV电力施工过程中为了有效的控制工程造价就必须做好合同管理。进行合同管理是为了有效的约束建设单位以及施工单位的行为,将双方的责任和义务进行明确地划分。为了有效的控制工程造价需要对建设项目中对工程造价造成影响的因素进行有效的控制,在合同中做好明确地规定。由于电力施工过程中会出现许多可预测以及不可预测的变动,所以应该在合同中对这些变动进行详细的说明,避免之后合同双方出现双扯皮现象。
在电力项目施工合同的拟定过程中,业主为了维护自身的经济利益,在制定招标文件以及施工合同的同时会将一些不利因素隐含到合同当中。由于施工单位在进行谈判时通常会受到业主方的限制,承担较大的风险因素,施工单位在签订施工合同时应该对合同中的条例进行详细的分析,并正确分析业主的意图,只有做到知己知彼,在施工过程中才能有效的避免风险因素,做到百战百胜。
在电力工程施工过程中材料费以及设备费用占工程造价的百分之六十以上,所以在合同管理阶段要加强对设备、材料费用的管理。施工过程中工程进度款的支付是以施工合同为依据。在电力施工过程中经常出现设计变更的现象,而合同则是控制合同变更的依据。进行设计变更之后,必须做好签证工作,按照合同规定进行价款的调整,有效避免竣工阶段出现双扯皮现象。
合同管理是进行工程索赔的依据。在进行造价管理的过程中,应该加强索赔的主动性,根据合同条款以及相关规定对费用索赔以及工期索赔进行合理的控制。在进行工期索赔时,应该认证分析是否是关键工序的延误来判断是否进行工期索赔,并分析造成工期延误的原因,来划分双方的责任。竣工过程中根据承包合同、设计变更以及签证、造价相关的会议记录等方面的内容为依据作为竣工阶段索赔的依据。
三、电力线路造价控制
为了有效的控制工程造价应该从变电站的厂址选择,线路选择等方面来进行造价管理。应该选择线路长度较短、曲折系数较小。施工难度较低的路径。并且有合理规划和选择塔形以及桿塔基础,进而保证工程造价管理工作的顺利开展。
3.1、合理优化线路是控制电力工程造价的有效手段。
电力工程施工过程中降低工程造价最直接有效的方式就是对输电线路进行优化和设计。选择合理的路径是做好造价管理的重要手段。为了保证电力工程造价管理工作的顺利开展,在项目设计过程中,应该严格按照线路所处环境的实际地质、交通、气候条件对线路进行合理的优化设计。在进行线路优化的过程中应该充分考虑到施工的难易程度、造价控制以及安全等方面的内容,并且要保证对通信、军事设备的避让。而不是一味的追求输电线路的最短化。
3.2、选择合适的地线、导线是控制电力工程造价的有效手段。
实际施工过程中在进行地线以及导线的选择过程中,应综合考虑导线制造、线路的输送目的地负荷容量及负荷增长情况、运行维护等一些列的因素,进行合理的分析以及经济比较。保证导线和地线在发挥其设计性能的同时,有效的降低工程成本,来保证造价管理工作的顺利开展。
3.3、选择合适的塔形是控制电力工程造价的有效手段。
众所周知,在进行电力线路的优化过程中,塔形的规划和选择是极为重要的。选择合适的塔形可以有效的降低塔材的使用量,进而降低工程造价。在进行塔形的规划时,应该综合占地面积、工程造价、运输以及安全等各方面的因素,进行综合的分析和判断。在设计阶段应该根据施工实际情况进行他性的选择,在保证功能的同时,提高直型塔的使用量,最大限度降低线路的曲折系数,选择耗材量小的杆型。除此之外,还可以使用双回路以及多回路铁塔等来进行线路的规划,进而合理的控制工程造价。
3.4、合理的优化杆塔基础是控制电力工程造价的有效手段
在电力工程施工过程中,杆塔的基础时输电线路的重要组成部分,并且杆塔基础的施工占据了整个电力线路施工周期的一半时间。对整个电力工程的施工进度以及工程造价都有着极为重要的影响。为了实行配电线路的合理规划,有效的进行造价控制,就必须合理规划杆塔基础。
四、成本控制是进行造价管理的必要手段。
为了提高施工企业的行业竞争力,提高经济效益,施工单位要做好成本控制。在施工过程中制定合理的计划来有效地降低工程成本。这就要求施工单位从组织方面和技术方面双管齐下,来降低工程成本。施工单位可以使用先进的机械设备和施工工艺技术,来提高工作效率,降低工程成本。
在对工程成本进行管理的过程中应本着全面控制的原则进行管理。这就要求对施工单位的全企业、全部施工人员以及施工全过程进行控制。
为了提高施工企业的行业竞争力,提高经济效益,施工单位要做好成本控制。在施工过程中制定合理的计划来有效地降低工程成本。这就要求施工单位从组织方面和技术方面双管齐下,来降低工程成本。施工单位可以使用先进的机械设备和施工工艺技术,来提高工作效率,降低工程成本。
结束语:随着电力行业的发展,施工单位为了提高经济效益,增强行业竞争力就必须加强对电力施工过程中的造价管理。文章中笔者结合110KV输电线路的规划,从合同管理以及成本控制等方面对电力工程的工程造价管理进行研究。使得电力施工过程在保证工程质量的同时,来进一步提高经济效益促进电力行业的长足发展。
参考文献:
[1]电力建设工程预算定额第四册送电线路工程(2006年版)[S].北京:中国电力出版社,2007.
[2]徐春凤.电力施工企业工程造价管理中存在的问题及改善对策[J].电力科技,2012
[3]颜柬华.浅谈电力施工企业工程造价管理[J].工程管理,201
[4]. 李铁国.浅谈电力工程的造价管理与控制措施[J].科技资讯.2007(36)