论文部分内容阅读
在批林批孔运动普及、深入、持久发展的大好形势下,遵照毛主席关于“我们必须打破常规,尽量采用先进技术”的教导,在某电站100米烟囱施工中,学习兄弟单位的先进经验,采用了无井架液压滑模施工,并组成以工人为主体的三结合小组,对双滑、自动同步控制和激光对中等新技术进行了研究和应用,收到较好的效果。经过广大职工日夜奋战,共用了38个工作日胜利地完成囱壁和内衬的滑升施工任务(图1)。
Under the favorable situation of popularizing, deepening, and sustaining development of the approved batches of forests and holes, follow the guidance of Chairman Mao on “We must break the routine and use advanced technologies as much as possible” to learn the advanced experience of our brothers in the construction of a 100-meter chimney at a power station. The use of a hydraulic gantry construction without derricks and the formation of a three-combination group with workers as the main body, researches and applies new technologies such as double-sliding, automatic synchronization control, and laser-to-medium technology, and has received good results. After working hard day and night, the company shared 38 working days to complete the sliding construction task of the chimney wall and lining (Figure 1).