在电力自动化研究院自控所和富春江水力发电厂的共同努力下,该厂计算机实时监控系统改造升级工程第一阶段投运各项工作已于1998年3月18日顺利完成。该项工程合同于去年8月在富春江电厂签订,仅4个月时间,第一批设备就发运到现场。由于电厂检修计划的调整,今年3月初开始投运,仅用了两周多的时间,全部一期设备投运完毕。现富
With the joint efforts of the Automation Institute of Power Automation and the Fuchunjiang Hydropower Plant, the first phase of the transformation and upgrading project of the computer real-time monitoring system was successfully completed on March 18, 1998. The project contract was signed in Fuchunjiang Power Plant in August last year. Only four months later, the first batch of equipment was shipped to the site. Due to the adjustment of the maintenance plan of the power plant, it was put into operation in early March of this year. It took only two weeks or so, and all the first-phase equipment was put into operation. Now rich