锦凌水库工程位于锦州市境内的小凌河干流上,坝址位于锦州市近郊区的后山河营子村,距锦州市中心9.5 km。水库工程施工主要包括土石方明挖、砂砾料填筑、黏土及混凝土浇筑等施工项目。根据施工进度计划安排,土石方开挖不需要进行冬季施工,气候对施工影响不大,主要是雨季施工防护;坝体填筑冬季不施工,因此针对以上施工项目特点,在特殊季节施工中采取切实可行的措施,以保证施工进度和施工质量。
Jinling Reservoir Project is located in the main stream of Jinling City in the Ling River, dam site is located in the suburbs of Jinzhou City, Hou Shanhe Yingzi Village, from the center of Jinzhou 9.5 km. The construction of reservoirs mainly includes earthwork excavation, sand and gravel filling, clay and concrete pouring and other construction projects. According to the construction schedule, the excavation of earth and stone does not need to be carried out in winter, and the climate has little effect on the construction, mainly due to the construction protection during the rainy season. The construction of the dam will be completed in winter and will not be constructed. Therefore, in light of the above construction projects, Feasible measures to ensure the construction progress and construction quality.