我国自行设计建造的秦山30万千瓦核电站,经过81个月的建造与调试,于1991年12月15日并网发电成功,结束了中国大陆无核电的历史,树立了中国核电发展史上的重要里程碑。大亚湾核电站两台百万千瓦级机组,先后于1993年8月31日和1994年2月7日并网发电成功,树立了利用外资建造大型核电站的典范。岭澳核电站和秦山第二、第三核电站主体工程正加紧施工,连云港核电站即
After its 81 months of construction and commissioning, Qinshan 300,000-kilowatt nuclear power station designed and built by China itself succeeded in grid-connected power generation on December 15, 1991, ending the history of non-nuclear power generation in mainland China and setting an important milestone in the development history of nuclear power in China. . Two million-kilowatt units of Daya Bay Nuclear Power Station were successfully connected to the grid on August 31, 1993 and February 7, 1994, setting a good example of using foreign capital to build large-scale nuclear power plants. Ling Ao Nuclear Power Station and Qinshan second and third nuclear power plants are stepping up the construction of the main project, namely Lianyungang Nuclear Power Station