四川省档案馆前馆基建工程,自一九八五年三月破土动工以来,在省委、省政府的关怀下,在有关部门的支持和设计、施工、建设单位的共同努力下,进展较为顺利:一九八五年建成了地下人防工程869平方米和主楼地上部分框架;一九八六年五月,建筑面积11000余平方米的主楼地上十六层框架封顶断水;五月以后室内外安装、装饰施工陆续展开;到一九八六年底,主楼完成了各层磨石地坪制作,窗台墙、内墙的砌筑,空调通风管道的安装和部分消防、电气管道的敷设;裙楼基础即将浇灌;地下水池、水泵房、配电房和宿舍等子项工程施工已全面铺开。
Since the groundbreaking of the former archives of Sichuan Provincial Archives Project started in March 1985, thanks to the concern of the provincial party committee and the provincial government, with the support of relevant departments and the concerted efforts of design, construction and construction units, Smooth: 869 square meters of underground civil air defense works and part of the ground floor of the main building were completed in 1985; in May 1986, the ground floor of the main building with a building area of 11,000 square meters was covered with a ceiling for water suspension; and after May, Installation and decoration started one after another. By the end of 1986, the main building had completed the production of grindstone floors of various floors, the installation of windowsill walls and masonry walls, air-conditioning ventilation ducts and part of fire control and electric pipes; the podium The foundation is about to be irrigated; construction of sub-projects such as underground water tanks, pump houses, power distribution rooms and dormitories has been fully carried out.