摘要:目的:讨论某度假酒店山体边坡治理方法。方法:根据文献资料与多年经验进行归纳总结。结果:土方回填-锚杆工程-土方开挖-锚杆工程-如此反复至基础-挡土墙施工-消防路面施工-格构梁施工。结论:根据本工程实际情况,土方工程必须采用先回填再分层开挖的方法。锚杆杆体采用3C 25HRB400级钢筋点焊成束,锚头采用3C25HRB400级钢筋与锚杆双面满焊或锚杆杆体钢筋直接弯钩,对中支架采用φ12钢筋与锚杆钢筋点焊连接。边坡采用钢筋混凝土格构梁+挡土墙+锚杆的支护方式。
关键字:山体;边坡;治理;加固
Abstract: Objective: To discuss the treatment method of a resort hotel mountain slope. Methods: Based on the literature and years of experience summarized. Results: Earthwork backfill - the anchor project - earth excavation - bolt works - and so forth to the foundation - retaining wall - Fire road construction - lattice girder construction. Conclusion: According to the actual situation of the works, earthworks must be used first backfill stratified excavation method. The anchor rod using 3C 25HRB400 grade steel welding beam, anchor head with hook 3C25HRB400 grade steel with full bolt-sided welding or bolt rod reinforced directly φ12 steel and bolt steel spot welding on the bracket. Slope reinforced concrete lattice beam + retaining wall + bolt the support method.
Keywords: mountain; slope; governance; reinforcement
中图分类号:U456.2文献标识码:A 文章编号:
天津蓟县圣光温泉旅游度假酒店工程位于天津市蓟县,总建筑面59286㎡,地下一层,地上五层,建筑高度23.95m,結构类型为框架结构。
施工顺序
土方回填-锚杆工程-土方开挖-锚杆工程-如此反复至基础-挡土墙施工-消防路面施工-格构梁施工。
主要施工内容
一、土方工程
根据本工程实际情况,土方工程必须采用先回填再分层开挖的方法,具体土方量详见土方方格网图及现场签证。
1.土方回填
山体为一定角度的坡面,要在山体表面施工必须创造施工面。故回填与山体坡面平行,宽度为5m的回填土,回填至距坡顶2m。如图1所示
图1
1)土方回填施工工艺
山体表面及基坑底地坪上清理→检验土质→分层铺土→分层碾压密实→检验密实度→修整找平验收
(1)填土前,应将基土上的洞穴或表面上的树根、垃圾等杂物都处理完毕,清除干净。
(2)检验土质。检验回填土料的种类、粒径,有无杂物,是否符合规定,以及土料的含水量是否在控制范围内;如含水量偏高,可采用翻松、晾晒或均匀掺入干土等措施;如遇填料含水量偏低,可采用预先洒水润湿等措施。
(3)填土应分层铺摊。每层铺土的厚度应根据土质、密实度要求和机具性能确定。填土每层的铺土厚度和压实遍数压实机具每层铺土厚度 300(mm)。
(4)打夯时,夯迹应相互搭接,防止漏压或漏夯。长宽比较大时,填土应分段进行。每层接缝处应做成斜坡形,碾迹重叠。重叠0.5~l.0m左右,上下层错缝距离不应小于1m。
(5)在机械施工碾压不到的填土部位,应配合人工推土填充,用蛙式或柴油打夯机分层夯打密实。
(6)回填土方每层压实后,应按规范规定进行环刀取样,测出干土的质量密度,达到要求后,再进行上一层的铺土。
2.土方开挖
1)土方开挖施工工艺
测量放线→确定开挖顺序和坡度→分段、分层均匀开挖→排(降)水→修坡和清底→坡道收尾。
(1)基坑开挖,应先测量定位,抄平放线,定出开挖宽度,按放线分块(段)分层挖土。
(2)开挖深度按整体大面标高确定,土方开挖由专人指挥,采取分段开挖,当挖至标高接近设计标高时,边抄平边配合人工清槽,防止超挖,并及时修整边坡及放坡,防止土方坍塌。
2)土方开挖注意事项
(1)边坡开挖应自上向下进行,开挖一层,施工一层锚杆,严禁超挖;
(2)开挖过程中严禁施工坡率大于设计坡率;
(3)边坡开挖过程中,距设计坡面20cm应留置人工开挖层,严禁机械开挖一次到位;
(4)格构梁及面层沟槽应采用人工开挖;
二、锚杆工程
锚杆杆体采用3C 25HRB400级钢筋点焊成束,锚头采用3C25HRB400级钢筋与锚杆双面满焊或锚杆杆体钢筋直接弯钩,对中支架采用φ12钢筋与锚杆钢筋点焊连接。具体详见图2
图2
三、护坡工程
边坡采用钢筋混凝土格构梁+挡土墙+锚杆的支护方式
1.格构梁施工要点
1)格构梁宽度为400mm,厚度400mm,格构梁纵向主筋采用C25的HRB400级钢筋,箍筋采用φ12的HRB235级钢筋,格构水平间距为1500mm,竖向间距为1500mm。格构梁混凝土采用C30。具体详见图3
图3
2)格构梁模板采用15mm厚木胶合板制作,采购原板规格1220mm×2440mm,梁侧采用C14间距600mm支撑。如图4所示
图4
3)消防通道路面标高(大沽高程69.55m)以上采用钢筋混凝土格构梁,格间采用钢筋混凝土面层,厚度为100mm,采用φ8的HRB235级钢筋双向配筋,与格构梁连结成整体。具体详见图5
图5
4)钢筋混凝土构件保护层厚度不小于50mm。
5)钢筋混凝土格构梁及钢筋混凝土面层施工前应清除溜滑体、蠕滑体和松动岩块,保证过程安全。
6)钢筋混凝土面层可采用喷射混凝土方式。
2.挡土墙施工要点
由于挡土墙部分尚在设计计算中,故暂无挡土墙节点图纸。
1)挡土墙每隔25米设置一道变形缝;缝宽20mm~30mm,填塞沥青麻筋或沥青木板。
2)挡土墙下方设置载水沟,截水沟在施工时采用人工开挖沟槽,沟壁应夯实平整,然后支模浇筑C20混凝土。截水沟应与排水管网联通。
3.护坡工程注意事项
1)格构梁钢筋应避免污染,使用前应除锈。
2)混凝土的浇注应架设模板,模板应加支撑固定;与岩石接触处可不架设模板,混凝土紧贴岩石浇筑。
3)坡面每隔3m,上下左右交错设置泄水孔,最下一排泄水孔须高出地0.2m,泄水孔采用直径125mm圆形孔,深度为50cm,泄水孔进水侧需用土工布进行包裹,以防堵塞。泄水孔内部反滤包尺寸应大于孔径1.5倍,保证有效过滤及不堵塞泄水孔。
五、边坡监测
由于岩土工程的复杂性,边坡支护系统受到许多难以确定的因素的影响,须对边坡支护系统进行监测,详细掌握边坡支护及使用过程中的情况,做到信息化施工。
监测主要内容如下:
本边坡按照一级边坡进行监测,在工程竣工后监测时间不应少于二年。
监测频率:施工期间每15天观测1次,竣工后两年内每30天观测1次。
边坡监测由建设单位直接委托有资质的监测单位编制方案,经设计、监理和建设单位等共同确认后实施,方案必须包括上述监测项目、监测目的、测试方法、测点布置、监测项目报警值、信息反馈制度和现场原始状态资料记录等内容。对监测结果应及时进行反馈,发现异常情况应及时通知设计人员,以便研究解决方案。
六、质量检测
1)执行规范《建筑边坡工程技术规范》GB50330-2002;
2)常规检测:施工用原材料水泥、钢筋、锚索、砂、碎石等;
3)注浆体强度检验试块数量每30根锚杆不小于一组;
4)锚杆抗拔力检验;
5)格构梁混凝土试块强度检验;
6)具体检测数量可按有关规范,由业主、监理、设计及施工单位共同协商确定。
参考文献:
朱彦鹏,李忠.深基坑土钉支护稳定性分析方法的改进及软件开发[J]. 岩土工程学报, 2005, 27(8):939-943.
陈祖煜著.土质边坡稳定分析—原理、方法、程序. [M].北京:水利电力出版社,2000
李海光. 新型支挡结构设计与工程实例 [M]. 北京: 人民交通出版社, 2004, 2.
朱彦鹏,王秀丽,狄生奎,等.黄土边坡建筑的抗滑移设计[J].甘肃工业大学学报,2002,28(2):85-89.
关键字:山体;边坡;治理;加固
Abstract: Objective: To discuss the treatment method of a resort hotel mountain slope. Methods: Based on the literature and years of experience summarized. Results: Earthwork backfill - the anchor project - earth excavation - bolt works - and so forth to the foundation - retaining wall - Fire road construction - lattice girder construction. Conclusion: According to the actual situation of the works, earthworks must be used first backfill stratified excavation method. The anchor rod using 3C 25HRB400 grade steel welding beam, anchor head with hook 3C25HRB400 grade steel with full bolt-sided welding or bolt rod reinforced directly φ12 steel and bolt steel spot welding on the bracket. Slope reinforced concrete lattice beam + retaining wall + bolt the support method.
Keywords: mountain; slope; governance; reinforcement
中图分类号:U456.2文献标识码:A 文章编号:
天津蓟县圣光温泉旅游度假酒店工程位于天津市蓟县,总建筑面59286㎡,地下一层,地上五层,建筑高度23.95m,結构类型为框架结构。
施工顺序
土方回填-锚杆工程-土方开挖-锚杆工程-如此反复至基础-挡土墙施工-消防路面施工-格构梁施工。
主要施工内容
一、土方工程
根据本工程实际情况,土方工程必须采用先回填再分层开挖的方法,具体土方量详见土方方格网图及现场签证。
1.土方回填
山体为一定角度的坡面,要在山体表面施工必须创造施工面。故回填与山体坡面平行,宽度为5m的回填土,回填至距坡顶2m。如图1所示
图1
1)土方回填施工工艺
山体表面及基坑底地坪上清理→检验土质→分层铺土→分层碾压密实→检验密实度→修整找平验收
(1)填土前,应将基土上的洞穴或表面上的树根、垃圾等杂物都处理完毕,清除干净。
(2)检验土质。检验回填土料的种类、粒径,有无杂物,是否符合规定,以及土料的含水量是否在控制范围内;如含水量偏高,可采用翻松、晾晒或均匀掺入干土等措施;如遇填料含水量偏低,可采用预先洒水润湿等措施。
(3)填土应分层铺摊。每层铺土的厚度应根据土质、密实度要求和机具性能确定。填土每层的铺土厚度和压实遍数压实机具每层铺土厚度 300(mm)。
(4)打夯时,夯迹应相互搭接,防止漏压或漏夯。长宽比较大时,填土应分段进行。每层接缝处应做成斜坡形,碾迹重叠。重叠0.5~l.0m左右,上下层错缝距离不应小于1m。
(5)在机械施工碾压不到的填土部位,应配合人工推土填充,用蛙式或柴油打夯机分层夯打密实。
(6)回填土方每层压实后,应按规范规定进行环刀取样,测出干土的质量密度,达到要求后,再进行上一层的铺土。
2.土方开挖
1)土方开挖施工工艺
测量放线→确定开挖顺序和坡度→分段、分层均匀开挖→排(降)水→修坡和清底→坡道收尾。
(1)基坑开挖,应先测量定位,抄平放线,定出开挖宽度,按放线分块(段)分层挖土。
(2)开挖深度按整体大面标高确定,土方开挖由专人指挥,采取分段开挖,当挖至标高接近设计标高时,边抄平边配合人工清槽,防止超挖,并及时修整边坡及放坡,防止土方坍塌。
2)土方开挖注意事项
(1)边坡开挖应自上向下进行,开挖一层,施工一层锚杆,严禁超挖;
(2)开挖过程中严禁施工坡率大于设计坡率;
(3)边坡开挖过程中,距设计坡面20cm应留置人工开挖层,严禁机械开挖一次到位;
(4)格构梁及面层沟槽应采用人工开挖;
二、锚杆工程
锚杆杆体采用3C 25HRB400级钢筋点焊成束,锚头采用3C25HRB400级钢筋与锚杆双面满焊或锚杆杆体钢筋直接弯钩,对中支架采用φ12钢筋与锚杆钢筋点焊连接。具体详见图2
图2
三、护坡工程
边坡采用钢筋混凝土格构梁+挡土墙+锚杆的支护方式
1.格构梁施工要点
1)格构梁宽度为400mm,厚度400mm,格构梁纵向主筋采用C25的HRB400级钢筋,箍筋采用φ12的HRB235级钢筋,格构水平间距为1500mm,竖向间距为1500mm。格构梁混凝土采用C30。具体详见图3
图3
2)格构梁模板采用15mm厚木胶合板制作,采购原板规格1220mm×2440mm,梁侧采用C14间距600mm支撑。如图4所示
图4
3)消防通道路面标高(大沽高程69.55m)以上采用钢筋混凝土格构梁,格间采用钢筋混凝土面层,厚度为100mm,采用φ8的HRB235级钢筋双向配筋,与格构梁连结成整体。具体详见图5
图5
4)钢筋混凝土构件保护层厚度不小于50mm。
5)钢筋混凝土格构梁及钢筋混凝土面层施工前应清除溜滑体、蠕滑体和松动岩块,保证过程安全。
6)钢筋混凝土面层可采用喷射混凝土方式。
2.挡土墙施工要点
由于挡土墙部分尚在设计计算中,故暂无挡土墙节点图纸。
1)挡土墙每隔25米设置一道变形缝;缝宽20mm~30mm,填塞沥青麻筋或沥青木板。
2)挡土墙下方设置载水沟,截水沟在施工时采用人工开挖沟槽,沟壁应夯实平整,然后支模浇筑C20混凝土。截水沟应与排水管网联通。
3.护坡工程注意事项
1)格构梁钢筋应避免污染,使用前应除锈。
2)混凝土的浇注应架设模板,模板应加支撑固定;与岩石接触处可不架设模板,混凝土紧贴岩石浇筑。
3)坡面每隔3m,上下左右交错设置泄水孔,最下一排泄水孔须高出地0.2m,泄水孔采用直径125mm圆形孔,深度为50cm,泄水孔进水侧需用土工布进行包裹,以防堵塞。泄水孔内部反滤包尺寸应大于孔径1.5倍,保证有效过滤及不堵塞泄水孔。
五、边坡监测
由于岩土工程的复杂性,边坡支护系统受到许多难以确定的因素的影响,须对边坡支护系统进行监测,详细掌握边坡支护及使用过程中的情况,做到信息化施工。
监测主要内容如下:
本边坡按照一级边坡进行监测,在工程竣工后监测时间不应少于二年。
监测频率:施工期间每15天观测1次,竣工后两年内每30天观测1次。
边坡监测由建设单位直接委托有资质的监测单位编制方案,经设计、监理和建设单位等共同确认后实施,方案必须包括上述监测项目、监测目的、测试方法、测点布置、监测项目报警值、信息反馈制度和现场原始状态资料记录等内容。对监测结果应及时进行反馈,发现异常情况应及时通知设计人员,以便研究解决方案。
六、质量检测
1)执行规范《建筑边坡工程技术规范》GB50330-2002;
2)常规检测:施工用原材料水泥、钢筋、锚索、砂、碎石等;
3)注浆体强度检验试块数量每30根锚杆不小于一组;
4)锚杆抗拔力检验;
5)格构梁混凝土试块强度检验;
6)具体检测数量可按有关规范,由业主、监理、设计及施工单位共同协商确定。
参考文献:
朱彦鹏,李忠.深基坑土钉支护稳定性分析方法的改进及软件开发[J]. 岩土工程学报, 2005, 27(8):939-943.
陈祖煜著.土质边坡稳定分析—原理、方法、程序. [M].北京:水利电力出版社,2000
李海光. 新型支挡结构设计与工程实例 [M]. 北京: 人民交通出版社, 2004, 2.
朱彦鹏,王秀丽,狄生奎,等.黄土边坡建筑的抗滑移设计[J].甘肃工业大学学报,2002,28(2):85-89.