我局接管工作,在二月間已告一段落,三月初、各部門的業務,已正式開展,按照預定計劃積極推動,除工作進度,業已分旬呈報外,今再將三四月份的工作,綜合報告如次:一、衛生工作:(一)修建下水道,共已完成三千八百一十一公尺,即四公里弱,超過預定進度百分之二十五,其中石溝爲一一五九公尺,水泥管溝一○八六公尺。至修溝地區,包括本市筷子街、過街樓、陝西街、民族路、姚家巷、金沙崗、打鐵街、曹家巷、節約街、臨江門拱橋洞、若瑟堂巷、民生路、中華路、勝利大廈前、中二路、中四路、飛來寺、飛來寺公路、兩路口小學、中一路、羅家灣、牛角沱、特園路、曙樓內等處。(二)修建公厠:四月底以前,共完成市府內及華一村公厠三座,牛角沱、棗子嵐埡兩處公厠,均以完成蓋瓦工作,較場口、神仙洞、黃家埡口三處公厠,不在三四月份修建計劃內,亦已提前將其脚糞完成。(三)製造水泥管:兩個月共計完成混凝土溝管一千六百零八根,又混凝土窨井四十怏。(四)開採石料:於王園及遺愛祠兩處設廠開採,共開石料一千五百立公方,以供不應求,復於猪石壩開採石料約四百立公方。
Our office has taken over the work. It has come to an end in February. In early March, the business of various departments has been officially launched. According to the plan, it is actively promoted. Except for the progress of work, which has been reported lately, the work in March and April will be consolidated again The report is organized as follows: 1. Health work: (i) Sewer lines have been constructed, for which a total of 3811 meters has been completed, that is, four kilometers in length, more than 25% of the scheduled progress, of which 115% Nine meters, cement trench 1086 meters. To repair the ditch area, including the city’s chopsticks Street, crossing the street, Shaanxi Street, Minzu Road, Yao Lane, Sands Gang, Blacksmith Street, Cao Lane, Saving Street, Linjiang Arch Bridge hole, Joseph Hall Lane, Minsheng Road, China Road, Shengli Building, Zhong Er Road, Zhong Si Road, Fei Lao Temple, Fei Lao Si Road, two crossing primary school, all the way, Luo Jia Wan, Niujiao Tuo, Te Yuen Road, and other places inside. (B) the construction of public toilets: before the end of April, completed a total of three municipal public toilets and Huayi Village, Niujituotuo, dates Lanla two public toilets, are completed tiling work, more than the mouth, Shenxian Dong, Huang Jia Pass Three public toilets are not built in March or April and have completed their foot excretion in advance. (C) the manufacture of cement pipe: a total of two months to complete the concrete ditch pipe one thousand six hundred and eight, but also concrete manhole forty meters. (D) quarrying: In Wang Yuan and the Temple of Ai two factories set up a total of a stone opened a thousand five hundred public square, in short supply, rehabilitation of stone dam quarry about four hundred square meters.