论文部分内容阅读
一、工程概况北京清河毛纺动力厂一期工程,安装有一台6000kW发电机组和二台35t/h链条锅炉,主厂由汽机房、除氧煤仓间、锅炉房组成,平面柱距布置见图1。
I. Project Overview The first phase of the Beijing Qinghe Woolen Power Plant has installed a 6000kW generator set and two 35t/h chain boilers. The main plant consists of a steam turbine room, an oxygen-scavenging coal bunker room, and a boiler room. 1.