秘鲁是拉丁美洲水力蕴藏量第三大国,仅次于巴西和哥伦比亚,总量超过60 000 MW,但是只开发了其中的5%或3 000 MW。为了改善这一局面,秘鲁政府采取各种法律和经济手段来刺激新水电工程的开发,努力增加各类可再生能源的发电量。在可再生能源(RER)工程的首次国内招标中,选定了17项小于20 MW的水电工程。概述了秘鲁电力系统的状况,并对选中的17项工程中的其中的一项,即正在施工的19.2 MW的钱凯工程的概况及施工进展进行了介绍。
Peru is the third largest hydropower reservoir in Latin America, second only to Brazil and Colombia, with a total of more than 60,000 MW, but only 5% or 3,000 MW of them have been developed. In order to ameliorate the situation, the Peruvian government has taken various legal and economic measures to stimulate the development of new hydropower projects and strive to increase the generation of various types of renewable energy. In the first domestic tender for Renewable Energy (RER) projects, 17 hydropower projects of less than 20 MW were selected. An overview of the state of the electricity system in Peru was made and an overview of the construction of the 19.2 MW Qian Kai Project under construction and the progress of the construction were presented.