唐钢炼铁厂北区1#高炉扩容大修工程,是唐钢建安公司第二次采用高炉推移技术的综合性技改项目。主要包括高炉本体及附属设施的拆除,炉基、高炉框架局部保护性拆除,将新建2000立方米高炉整体推移就位,安装和恢复附属设施等项工作,计划工期45天。通过全体员工的共同努力,在比计划工期提前6天完成大修任务的情况下,再次实现轻伤以上事故为零的目标。这一切全得益于开工前的周密部署,为施工提供了安全保障。
Tangshan Iron and Steel Company North # 1 blast furnace capacity expansion overhaul project is Tangshan Iron and Steel Company Jian’an the second time using blast furnace technology comprehensive technological transformation project. Mainly including the demolition of blast furnace body and ancillary facilities, local protective removal of furnace base and blast furnace framework, putting the newly built 2000 cubic meter blast furnace in place as a whole, installing and restoring ancillary facilities and other projects with a planned duration of 45 days. Through the concerted efforts of all staff, the completion of the overhaul task 6 days ahead of schedule will again achieve the goal of causing minor injuries and accidents above zero. All this benefited from the careful deployment prior to the start of construction, providing security for the construction.