时值寒冬腊月,但在松原市境内的松花江干流下六家子险工护岸工程建设现场,记者看到轰鸣的机械作业和沸腾的劳动场面打破了这里严寒的沉寂,大规模的冬季冰上石笼软体沉排护脚工程正紧张有序的进行着。 下六家子护岸工程是松花江干流最大最险的河道险工,江面开阔汛期风急浪大,对岸边淘刷严重,江岸坍塌逐年加剧,严重威胁着宁江区工农业生产和人民生活的安全。为确保工程质量,必须选择在严寒的冬季施工,在冰层厚度达50cm以上时把石笼装砌等工序完成,现在他们投入大型机械二十八台,人力三万多工日,不分昼夜,苦战十二天出色的完成了冰上石笼装砌任务。
The time of the winter twelfth lunar month, but in the Songhua River in the Songhua River under the six sub-sea bank protection construction site, the reporter saw roaring mechanical homework and boiling labor scene here broke the cold silence, large-scale winter ice cage Sinking software project is tense and orderly conduct. The next six sub-bank revetment projects are the largest and most dangerous river infantry workers in the main stream of the Songhua River. The floods in the open river are characterized by large winds and waves, serious scouring of the shore and the collapse of riverbanks year by year, which threaten the industrial and agricultural production and people’s lives in Ningjiang District Safety. In order to ensure the quality of the project, it is necessary to choose the construction in the cold winter. When the thickness of the ice layer is more than 50cm, the construction of the stone cage is completed. Now they have put into operation 28 large-scale machinery and more than 30,000 manpower for day and night , Fierce fighting twelve days to complete the task of installing the ice stone cage.