上海地铁4#线在上海体育馆站穿越地铁1#线,下行穿越段主要位于含水丰富的粘土地层中。为保证穿越施工的顺利进行,本次采用了人工地层水平冻结加固技术对地层进行了预加固,并实施暗挖施工。文章以该工程为背景,在进行地层冻结温度、应力、位移场耦合计算的基础上,借助车站结构加固、悬吊、托换等保护性措施,并在冻结过程中,利用卸压、控制冻结等方法,成功实现了车站的零距离立体换乘施工,希望对同类工程的施工有一定的借鉴意义。
Shanghai Subway Line # 4 traverses Subway Line 1 at Shanghai Stadium Station, and the descending cross section is mainly located in a clay-rich water-rich formation. In order to ensure the smooth progress through the construction, the strata were pre-reinforced with horizontal freezing and reinforcement techniques of artificial strata and the undercut construction was carried out. On the basis of this project, based on the coupled calculation of formation freezing temperature, stress and displacement field, with the protective measures such as reinforcement, suspension and underpinning of the station structure, and using the pressure relief during the freezing process to control the freezing And other methods, the successful realization of the station zero distance three-dimensional transfer construction, hoping for the construction of similar projects have some reference.