某水泥生产企业在水泥炉窑的窑头和窑尾各装1台型号为QC328/325-24.6-1.25/305的余热锅炉,正常工作压力为1.05MPa。余热锅炉投产运行后,锅炉运行中常常发现锅水呈间歇性黑褐色水的现象,影响锅炉安全运行。针对该现象笔者进行了具体的原因分析,提出了解决方法,并在实施过程中不断完善,取得了较好的效果。1锅炉和水处理情况此类余热锅炉通常为层状支管式结构,从上至下有数层密排热交换管,如上述型号的窑尾炉有12层,共分3个循环回路,其中1层至4层热交换管路与汽包为一个循环回路,5层至8层及9层至12层又分别与汽包形成二个循环回路.三个循环回路之间通过数根下降管连通;窑头炉有9层,由于热交换管路较少,分为二个循环回路。锅炉运行时将与水泥熟料热交换后产生的热空气从锅炉顶部引入,从上至下逐层通过热交换管进行热交换。其中窑头炉余热气的进气温度为400℃,窑尾炉余热气进气温度为325℃,极大的利用了水泥生产过程中的余热。
A cement manufacturer in the cement kiln kiln and kiln tail fitted with a model QC328 / 325-24.6-1.25 / 305 waste heat boiler, the normal working pressure of 1.05MPa. After the waste heat boiler is put into operation, it is often found in the boiler operation that the pot water is intermittently dark brown water, affecting the safe operation of the boiler. In view of this phenomenon, the author has carried on the concrete reason analysis, proposed the solution method, and unceasingly consummates in the implementation process, obtained the good result. 1 boiler and water treatment Such waste heat boiler is usually layered pipe structure, from top to bottom with several layers of dense heat exchange tubes, such as the above model kiln stove has 12 layers, is divided into three loops, of which 1 to 4 layers of heat exchange tubes and drums as a loop, 5 to 8 and 9 to 12 layers and the drum are formed two loop, respectively, between the three loop through a number of down pipes Connected; kiln furnace has 9 layers, due to heat exchange pipe less, is divided into two loops. The hot air generated by the heat exchange with the cement clinker during the operation of the boiler is introduced from the top of the boiler and is heat-exchanged layer by layer through the heat exchange tubes from top to bottom. Incineration furnace kiln exhaust gas inlet temperature is 400 ℃, kiln tailings furnace inlet heat temperature of 325 ℃, making great use of the cement production process of waste heat.